Permit: T21CM04116
Permit Details
Apply Date:
05/13/2021
Applicant:
Tucson Expediting & Development
Description:
TI: Layout and Equipment Modifications to Existing Full Service Counter, Sales Floor and Checkstand
Architects:
- Daniel Filuk
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Completed Inspections
Permit Status: Final
Permit Number: T21CM04116
Permit Description: TI: Layout and Equipment Modifications to Existing Full Service Counter, Sales Floor and Checkstand
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2021 | PLUMBING - PRE SLAB | TGAUSP | Approved | Approved for kitchen, okay to backfill and concrete |
| 11/01/2021 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | Approved for kitchen |
| 11/01/2021 | ELECTRIC - PROGRESS | TGAUSP | Approved | Approved for kitchen |
| 11/04/2021 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | Approved |
| 11/04/2021 | PLUMBING - PROGRESS | TGAUSP | Approved | Approved |
| 11/04/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | Approved |
| 11/16/2021 | FIRE - FINAL | MROSS | Approved | |
| 11/16/2021 | FIRE - KITCHEN EXH HOOD FINAL | MROSS | Approved | There is no type 1 kitchen hood and no suppression system. |
| 11/16/2021 | FIRE - ALARM FINAL | MROSS | Approved | There is no fire alarm system in the building |
| 11/16/2021 | FIRE SPKLR - FINAL | MROSS | Approved | There is no sprinkler system in the building |
| 11/16/2021 | BUILDING ABOVE CEILING | TGAUSP | Approved | - Approved |
| 11/16/2021 | BUILDING - PROGRESS | TGAUSP | Approved | - Approved |
| 11/16/2021 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | - Approved |
| 11/16/2021 | PLUMBING - ABOVE CEILING | TGAUSP | Approved | - Approved |
| 11/16/2021 | MECHANICAL - ABOVE CEILING | TGAUSP | Approved | - Approved |
| 11/16/2021 | MECHANICAL - PROGRESS | TGAUSP | Approved | - Approved |
| 11/19/2021 | BUILDING - FINAL | TGAUSP | Approved | Approved |
| 11/19/2021 | SHEET ROCK NAILING | TGAUSP | Approved | Approved |
| 11/19/2021 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
| 11/19/2021 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
| 11/19/2021 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |
| 11/19/2021 | FRAMING | TGAUSP | Approved | previously Approved |