Permit: T21CM04094
Permit Details
Apply Date:
05/13/2021
Applicant:
Inai Anzueto
Description:
SFR
Contractors:
- SILVA DIVERSIFIED CONSTRUCTION CO LLC
Permit Reviews
Permit Number - T21CM04094
Permit Status: C of o
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/13/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/10/2021 | COMPLETED |
| 07/01/2021 | RESUBMITTAL | 07/16/2021 | COMPLETED |
| 11/29/2021 | REVISION - - 1ST | 12/07/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM04094
Permit Description: SFR
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/05/2021 | PLUMBING - ROUGH, SOIL | ESTVENS | Approved | . Partial. Under slab only. |
| 11/10/2021 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | Approved |
| 11/10/2021 | BUILDING PRE-SLAB | WGALLAGHER | Approved | Approved |
| 11/30/2021 | EXT METAL CLIPS/EXT SHEATHING | TGAUSP | Approved | Approved |
| 11/30/2021 | ROOF NAILING | TGAUSP | Approved | Approved |
| 11/30/2021 | FRAMING | TGAUSP | Approved | Approved |
| 11/30/2021 | ELECTRIC - UFER | TGAUSP | Approved | Approved |
| 11/30/2021 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved for kitchen island |
| 12/14/2021 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | AP |
| 12/14/2021 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | AP |
| 12/15/2021 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | Approved |
| 01/25/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 01/25/2022 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Ap Clear eco |
| 03/21/2022 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | Approved |
| 03/21/2022 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | Approved |
| 04/20/2022 | PLUMBING - FINAL | ESTEVENS | Approved | Approved |
| 04/21/2022 | MECHANICAL - FINAL | WGALLAGHER | Approved | Approved |
| 04/21/2022 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 04/21/2022 | ELECTRIC - FINAL | WGALLAGHER | Approved | Approved |
| 04/21/2022 | BUILDING - FINAL | WGALLAGHER | Approved | Approved |