Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Address:
325 W ALASKA ST
Address NEW:
325 W ALASKA ST
Apply Date:
05/13/2021
Applicant:
Description:
Replacing trusses, Mechanical A/C Unit, Duct Work, Plumbing & Electrical Re-wire with panel upgrade

Permit Reviews

Permit Number - T21CM04089
Permit Status: Issued
Permit Description: Replacing trusses, Mechanical A/C Unit, Duct Work, Plumbing & Electrical Re-wire with panel upgrade
Start Date Submittal Complete Date Status  
05/13/2021 RESIDENTIAL - BLDG/WWM 05/13/2021 ACTIVE Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM04089
Permite Description: Replacing trusses, Mechanical A/C Unit, Duct Work, Plumbing & Electrical Re-wire with panel upgrade
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - RSME - Mechanical Final N/A Not Ready
10/27/2022 RSBU - Building Final N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready
10/27/2022 RSME - Mechanical Progress N/A Not Ready
10/26/2022 RSBU - Building Progress N/A Not Ready
10/26/2022 COT - RSEL - Service Upgrade N/A Not Ready
10/27/2022 COT - RSEL - Electrical Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T21CM04089
Permit Description: Replacing trusses, Mechanical A/C Unit, Duct Work, Plumbing & Electrical Re-wire with panel upgrade
Total Completed Inspections - 4
Date Description Inspector Results Comments
01/25/2022 RSEL - Electrical Progress Passed {Activity date: 01/25/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - intermediates approved, pending fire foam and framing} ; {Activity date: 01/06/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial electrical, pending frame and intermediates}
01/25/2022 RSPL - Plumbing Progress Passed {Activity date: 01/25/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - intermediate waterlines approved, pending fire foam and framing}
02/16/2022 COT - LCBU - Framing Passed {Activity date: 02/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to insulate and drywall} ; {Activity date: 01/25/2022; Status: Correction Required; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Corrections, fire blocking missing at several walls} ; {Activity date: 09/03/2021; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial, Roof nail is approved and okay to roof

}
07/11/2022 BULD - Electrical Clearance Passed {Activity date: 07/11/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - CODE INCR}

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
MANUAL J CALCS.PDF DOCUMENTS VIEW
PRODUCT RATINGS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW