Permit: T21CM04037
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
831 S BEVERLY AV
Address NEW:
831 S BEVERLY AV
Apply Date:
05/12/2021
Applicant:
Jesus Cedeno
Description:
Enclose porch into bedroom
Permit Reviews
Permit Number - T21CM04037
Permit Status: Issued
Permit Description: Enclose porch into bedroom
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/12/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/28/2021 | COMPLETED |
| 07/01/2021 | RESUBMITTAL | 07/16/2021 | COMPLETED |
| 11/16/2021 | REVISION - - 1ST | 11/23/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM04037
Permite Description: Enclose porch into bedroom
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Stem Wall/Retaining Wall | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM04037
Permit Description: Enclose porch into bedroom
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/07/2021 | COT - RSBU - Preslab | Passed | {Activity date: 12/07/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 12/07/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 12/07/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 12/07/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/07/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 01/11/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 01/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 01/10/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - DE. Provide ladder for roof access.} | |
| 01/11/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 01/11/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 01/10/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - DE. Provide approved plans.} | |
| 02/17/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/17/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CODE ECO} | |
| 03/22/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 01/28/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA per text from contact.} | |
| 03/22/2022 | COT - LCBU - Framing | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/17/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Plumbing Rough and ECO clearance only.} | |
| 03/22/2022 | RSME - Mechanical Progress | Passed | {Activity date: 03/22/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 02/15/2023 | COT - RSME - Mechanical Final | Passed | ||
| 02/15/2023 | RSBU - Building Final | Passed | ||
| 02/15/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 02/15/2023 | COT - RSEL - Electrical Final | Passed |