Permit: T21CM04008
Permit Details
Status:
Expired
Type:
Commercial Building
Address:
3224 N FREEWAY INDUSTRIAL LP 102
Address NEW:
3224 N FREEWAY INDUSTRIAL LP 102
Apply Date:
05/11/2021
Applicant:
Lisa Bowers
Description:
TI: Office/Storage
Permit Reviews
Permit Number - T21CM04008
Permit Status: Expired
Permit Description: TI: Office/Storage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/11/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/18/2021 | COMPLETED |
| 06/21/2021 | RESUBMITTAL | 07/12/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Expired
Permit Number: T21CM04008
Permite Description: TI: Office/Storage
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM04008
Permit Description: TI: Office/Storage
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2021 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/19/2021 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/19/2021 | COT - LCBU - Framing | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/19/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/19/2021 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/19/2021 | COT - LCBU - Building Progress | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/19/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 07/19/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap} | |
| 07/26/2021 | COT - LCEL - Electrical Progress | Passed | {Activity date: 07/26/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - AP Clear INCR} ; {Activity date: 07/19/2021; Status: Not ready for Inspection; Inspector: DQUINN; Comment: Entered by RSALDAT1 - nr - call for electric power connect when ready} |
|
| 07/26/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 07/26/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by RSALDAT1 - CODE INCR} | |
| 08/13/2021 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 08/13/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 08/13/2021 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 08/13/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 09/15/2021 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 09/15/2021 | COT - LCME - Mechanical Final | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 07/12/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION} | |
| 09/15/2021 | COT - LCME - Mechanical Progress | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 09/15/2021 | COT - LCEL - Outdoor Lighting | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 09/15/2021 | COT - LCBU - Preslab | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 09/15/2021 | COT - LCEL - Electrical Final | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 09/15/2021 | COT - LCPL - Plumbing Final | Passed | {Activity date: 09/15/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 07/12/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - WATER QUALITY REPORT REQUIRED PRIOR TO FINAL INSPECTION} | |
| 09/16/2021 | COT - FCON - Fire - Final | Passed | {Activity date: 09/16/2021; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } |