Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM03996
Permit Details
Apply Date:
05/11/2021
Applicant:
VORTEX ENGINEERING, INC.
Description:
Construction of Loading Docks - 3 Pier Docks each 132' in length at existing FedEx package handling facility
Contractors:
- RIO WEST DEVELOPMENT AND CONSTR *C*
Permit Reviews
Permit Number - T21CM03996
Permit Status: L of c
Permit Description: Construction of Loading Docks - 3 Pier Docks each 132' in length at existing FedEx package handling facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/11/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/17/2021 | COMPLETED |
| 06/24/2021 | RESUBMITTAL | 07/19/2021 | COMPLETED |
| 07/27/2021 | RESUBMITTAL | 08/09/2021 | COMPLETED |
| 09/24/2021 | REVISION - - 1ST | 09/27/2021 | COMPLETED |
| 10/11/2021 | RESUBMITTAL | 10/13/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM03996
Permit Status: L of c
Permit Description: Construction of Loading Docks - 3 Pier Docks each 132' in length at existing FedEx package handling facility
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/11/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T21CM03996
Permit Description: Construction of Loading Docks - 3 Pier Docks each 132' in length at existing FedEx package handling facility
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2021 | BUILDING - PROGRESS | DMUNIZ | Approved | Partial, dowel set for pier 2 ok to proceed. 7050 S PALO VERDE RD |
| 08/20/2021 | BUILDING - PROGRESS | DMUNIZ | Approved | Partial, dowel set for pier 2 ok to proceed 3350 E WESTCO PL |
| 08/27/2021 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Partial, Underground conduits installed North parking lot, ok to backfill progress. 3350 E WESTCO PL |
| 08/27/2021 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Partial, Underground conduits installed North parking lot, ok to backfill progress. |
| 09/09/2021 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved 7050 S PALO VERDE RD |
| 09/09/2021 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved 3350 E WESTCO PL |
| 10/05/2021 | FRAMING | TGAUSP | Approved | Approved for all 3 Piers, rough frame inspection complete, continuous sheathing on both sides of walls (typ) * T21CM03996 has 2 addresses - 3350 E Westco Pl and 7050 S PALO Verde* |
| 10/05/2021 | FRAMING | TGAUSP | Approved | Approved for all 3 Piers, rough frame inspection complete, continuous sheathing on both sides of walls (typ) * T21CM03996 has 2 addresses - 3350 E Westco Pl and 7050 S PALO Verde* |
| 10/18/2021 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
| 10/18/2021 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 10/29/2021 | NPPO - FINAL | DROBERTS | Approved | IS APPROVED 7050 S PALO VERDE RD |
| 10/29/2021 | SIGN - FINAL | DROBERTS | Approved | IS APPROVED 7050 S PALO VERDE RD |
| 10/29/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | IS APPROVED 7050 S PALO VERDE RD |
| 10/29/2021 | ENGINEERING - FINAL | DROBERTS | Approved | IS APPROVED 7050 S PALO VERDE RD |
| 10/29/2021 | ENGINEERING - FINAL | DROBERTS | Approved | IS APPROVED 3350 E WESTCO PL |
| 10/29/2021 | LANDSCAPE - FINAL | DROBERTS | Approved | IS APPROVED 3350 E WESTCO PL |
| 10/29/2021 | SIGN - FINAL | DROBERTS | Approved | IS APPROVED 3350 E WESTCO PL |
| 10/29/2021 | NPPO - FINAL | DROBERTS | Approved | IS APPROVED 3350 E WESTCO PL |
| 10/29/2021 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Approved 3350 E WESTCO PL |
| 10/29/2021 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Approved 7050 S PALO VERDE RD |
| 11/03/2021 | BUILDING - FINAL | TGAUSP | Approved | Partial, pending Fire approval |
| 11/03/2021 | ELECTRIC - FINAL | TGAUSP | Approved | - Approved |
| 11/03/2021 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | - Approved |
| 11/03/2021 | FIRE - FINAL | jfordney | Approved | Only waiting on under conveyor coverage. OK for TCO. Firewatch is not required because piers are constantly attended when in use. Each pier has 2 fire extinguishers and a fully funtioning overhead sprinkler system |
| 11/03/2021 | FIRE SPKLR - FINAL | jfordney | Approved | Only waiting on under conveyor cocerage |
| 03/01/2022 | RIGHT OF WAY - FINAL | jcazare1 | Approved | no right of way impact approved |