Permit: T21CM03883
Permit Details
Apply Date:
05/07/2021
Applicant:
Dora godinez
Description:
SFR
Contractors:
- silva diversified construction llc
Permit Reviews
Permit Number - T21CM03883
Permit Status: C of o
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/07/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/08/2021 | COMPLETED |
| 06/14/2021 | RESUBMITTAL | 06/15/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM03883
Permit Description: SFR
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/21/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | APPROVED 3 INCH TO 4 INCH TO SPETIC TANK. PCWW APPROVED |
| 06/21/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 06/23/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 06/23/2021 | ELECTRIC - UFER | DQUINN | Approved | |
| 06/23/2021 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 06/23/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 07/13/2021 | ROOF NAILING | DQUINN | Approved | Ap |
| 07/13/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | Ap |
| 08/03/2021 | FRAMING | DQUINN | Approved | Ap |
| 08/03/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | Ap |
| 08/03/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap 1. Redo gas test. 2. Screw toilet flanges to floor. 3. install platform and tpr drain for water heater. 4. Install bang plates where needed. 5. Move closet lights from shelving where needed. |
| 08/04/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
| 08/13/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 08/13/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Ap Clear eco |
| 08/24/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | Ap |
| 09/14/2021 | BUILDING - FINAL | DQUINN | Approved | APPROVED BY INSPECTOR AWAITING CONDITIONS |
| 09/14/2021 | GAS CLEARANCE | DQUINN | Approved | CODE |
| 09/14/2021 | SHEET ROCK NAILING | DQUINN | Approved | 1090 (BUILDING - FINAL) Ap |
| 09/14/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap Clear gas for new sfr Close permit |
| 09/14/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 09/14/2021 | SEPTIC - SYSTEM | DQUINN | Approved | Ap |
| 09/14/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap |
| 09/14/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 09/14/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 09/14/2021 | BUILDING - FINAL | DQUINN | Approved | Ap |