Permit: T21CM03833
Permit Details
Apply Date:
05/06/2021
Applicant:
Description:
SFR LENNVC454 T20-M0037
Outstanding Activity Conditions
Permit Number - T21CM03833
Permit Status: Expired
Permit Description: SFR LENNVC454 T20-M0037
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/06/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM03833
Permit Description: SFR LENNVC454 T20-M0037
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/26/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/26/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
05/26/2021 | COT - RSPL - Sewer | Passed | {Activity date: 05/26/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
05/26/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 05/26/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
06/22/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 06/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
06/22/2021 | COT - RSBU - Preslab | Passed | {Activity date: 06/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
06/22/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 06/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
06/22/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
08/02/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/02/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
08/02/2021 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/02/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
12/03/2021 | COT - LCBU - Framing | Passed | {Activity date: 12/03/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
12/03/2021 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 12/03/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
12/08/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 12/08/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 12/07/2021; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA per John Sutton } ; {Activity date: 12/03/2021; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CO 1. Gas bond is not sized per plan 2. Missing garage outlet on middle of long wall 3. Seal chase on 2nd floor} |
|
12/13/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 12/13/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 12/10/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not ready} | |
02/03/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO} | |
02/03/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 02/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP TEP ECO } |
|
03/01/2022 | COT - BULD - SWG Clearance | Passed | {Activity date: 03/01/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS} | |
03/17/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/17/2022 | RSBU - Building Final | Passed | {Activity date: 03/17/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/17/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
03/17/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA SWG clearance required} |
|
03/17/2022 | COT - RSEL - Electrical Final | Passed | {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} |