Permit: T21CM03547
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1402 E TUCSON MARKETPLACE BL
Address NEW:
1402 E TUCSON MARKETPLACE BL
Apply Date:
04/27/2021
Applicant:
Description:
NEW SHELL BUILDING
Permit Reviews
Permit Number - T21CM03547
Permit Status: Complete
Permit Description: NEW SHELL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2022 | REVISION - - 3RD | 02/28/2022 | COMPLETED |
| 04/28/2021 | 3RD PARTY REVIEW - COMMERCIAL | 06/29/2021 | COMPLETED |
| 04/30/2022 | REVISION - - 4TH | 05/24/2022 | COMPLETED |
| 06/29/2021 | POST 3RD PARTY REVIEW | 07/16/2021 | COMPLETED |
| 10/14/2021 | REVISION - - 1ST | 11/16/2021 | COMPLETED |
| 12/18/2021 | REVISION - - 2ND | 01/06/2022 | COMPLETED |
| 12/27/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/05/2023 | APPROVED |
| 12/16/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/19/2022 | APPROVED |
Conditions
Permit Number - T21CM03547
Permit Status: Complete
Permit Description: NEW SHELL BUILDING
| Date | Description | Comments |
|---|---|---|
| 01/05/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 06/29/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 06/29/2021 | SPECIAL INSPECTION IS REQUIRED FOR STRUCTURAL STEEL | |
| 06/29/2021 | SPECIAL INSPECTION IS REQUIRED FOR MASONRY | |
| 06/29/2021 | DEFERRED SUBMITTAL FOR I-JOISTS |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM03547
Permite Description: NEW SHELL BUILDING
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2022 | COT - LCBU - Masonry Pregrout | N/A | Canceled | {Activity date: 09/16/2022; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VVERA1 - N/A} |
| 10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| COT - FCON - Fire - Final | N/A | Canceled | ||
| 12/27/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
| 12/27/2022 | COT - LCEL - Outdoor Lighting | N/A | Not Ready | |
| 12/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| COT - FCON - Sprinkler - Final | N/A | Canceled | ||
| 12/27/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
| 12/19/2022 | COT - LCEL - Electrical Progress | N/A | Partial Pass | partial approval for temporary disconnect due to lack materials, ok to energize |
| 12/27/2022 | COT - LCEL - Grounding/Bonding | N/A | Not Ready | awaiting new switch gear |
| 12/27/2022 | COT - LCEL - Electrical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM03547
Permit Description: NEW SHELL BUILDING
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2022 | COT - LCPL - Yard Water Line | Passed | {Activity date: 03/03/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 03/17/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 03/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
| 04/07/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 04/07/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 04/27/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 04/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved, secondary conduits installed from SES to Transformer locations]. } ; {Activity date: 03/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - ) Partial, Under foundation raceways for feeders from Electrical room to panel location ok to backfill progress areas.} |
|
| 05/24/2022 | COT - LCPL - Plumbing Roof Drains | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
| 05/24/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 05/24/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for shell (T21CM03547) *Also verified and approved underground rough soil for pending TI (T22CM01578- DentalPro)} ; {Activity date: 03/03/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Ready} | |
| 09/16/2022 | COT - HCBU - Exterior Clips/Sheathing | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} | |
| 12/27/2022 | COT - LCBU - Framing | Passed | ||
| 12/27/2022 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
| 12/27/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 12/27/2022 | COT - LCPL - Sewer | Passed | ||
| 12/27/2022 | COT - LCME - Mechanical Final | Passed | ||
| 12/27/2022 | COT - LCBU - Building Above Ceiling | Passed | ||
| 12/27/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 12/27/2022 | COT - LCBU - Building Progress | Passed | ||
| 12/27/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | Passed | ||
| 12/27/2022 | COT - LCPL - Plumbing Progress | Passed | ||
| 12/27/2022 | COT - LCME - Mechanical Intermediate | Passed | ||
| 12/27/2022 | COT - LCBU - Preslab | Passed | ||
| 12/27/2022 | COT - LCEL - Construction Power | Passed | n/a | |
| 12/27/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 12/27/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 12/27/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 12/27/2022 | COT - LCME - Mechanical Progress | Passed | ||
| 12/29/2022 | COT - FCON - Fire - Final | Passed | ||
| 12/29/2022 | FCON – OH Piping & Hydro | Passed | ||
| 12/29/2022 | COT - LCBU - Sustainability | Passed | ||
| 12/29/2022 | COT - LCEL - Outdoor Lighting | Passed | ||
| 01/06/2023 | BULD - Electrical Clearance | Passed | ||
| 01/06/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/06/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/06/2023 | COT - LCBU - Building Final | Passed | ||
| 01/10/2023 | COT - FCON - Alarm - Final | Passed | Inspected by Will Motto | |
| 01/10/2023 | COT - FCON - Sprinkler - Final | Passed | Inspected by Will Motto on 12/29/22 | |
| 01/06/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 02/21/2023 | COT - LCEL - Electrical Progress | Passed | ||
| 02/23/2023 | COT - LCEL - Grounding/Bonding | Passed | ||
| 02/23/2023 | COT - LCEL - Electrical Final | Passed |