Permit Details

Status:
Final
Type:
COMMERCIAL OTHER
Address NEW:
140 S CAMINO SECO
Apply Date:
04/27/2021
Applicant:
Brent Miller Stand8
Description:
Remove 6 antennas(2 per sector); Remove (9)RRU's; Remove (1)hybrid cable 5/8" Install 6 antennas(2 per sector); Install 6 RRU's (2 per sector); Install (2) HCS 2.0 hybrid cables with pendant 1 1/2" Remove (1)SSC Cabinet; Remove (1) battery cabinet; Install (1) Purcell HPL3 SSC cabinet weattery cabinet; Install (2) HCS 2.0 Junction Box
Architects:
  • GDP Group
Contractors:
  • NORTHSTAR COMMUNICATIONS INC

Permit Reviews

Permit Number - T21CM03521
Permit Status: Final
Permit Description: Remove 6 antennas(2 per sector); Remove (9)RRU's; Remove (1)hybrid cable 5/8" Install 6 antennas(2 per sector); Install 6 RRU's (2 per sector); Install (2) HCS 2.0 hybrid cables with pendant 1 1/2" Remove (1)SSC Cabinet; Remove (1) battery cabinet; Install (1) Purcell HPL3 SSC cabinet weattery cabinet; Install (2) HCS 2.0 Junction Box
Start Date Submittal Complete Date Status  
04/28/2021 CELL TOWER/ANTENNAS 06/02/2021 COMPLETED Review Details
11/22/2021 REVISION - - 1ST 12/09/2021 COMPLETED Review Details

Completed Inspections

Permit Status: Final
Permit Number: T21CM03521
Permit Description: Remove 6 antennas(2 per sector); Remove (9)RRU's; Remove (1)hybrid cable 5/8" Install 6 antennas(2 per sector); Install 6 RRU's (2 per sector); Install (2) HCS 2.0 hybrid cables with pendant 1 1/2" Remove (1)SSC Cabinet; Remove (1) battery cabinet; Install (1) Purcell HPL3 SSC cabinet weattery cabinet; Install (2) HCS 2.0 Junction Box
Total Completed Inspections - 4
Date Description Inspector Results Comments
03/27/2022 ELECTRIC - SERVICE UPGRADE DMUNIZ1 Approved AFTER HOURS INSPECTION FOR METER/DISCONNECT UPGRADE. VERBAL CLEARANCE SENT TO TEP (INCR)
04/11/2022 FRAMING RCHANDLER Approved AP 1090
04/11/2022 ELECTRIC - FINAL RCHANDLER Approved AP
04/11/2022 BUILDING - FINAL RCHANDLER Approved AP