Permit: T21CM03490
Permit Details
Apply Date:
04/26/2021
Applicant:
Pm Design Group - Contact Jon Hughes
Description:
New Restaurant
Architects:
- Pm Design Group - Ken McCracken
Contractors:
- PARKWAY C&A LP
Permit Reviews
Permit Number - T21CM03490
Permit Status: C of o
Permit Description: New Restaurant
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/26/2021 | COMMERCIAL - NEW | 05/28/2021 | COMPLETED |
| 07/19/2022 | REVISION - - 1ST | 08/04/2022 | COMPLETED |
| 08/18/2022 | REVISION - - 1ST | 09/14/2022 | COMPLETED |
| 08/27/2021 | RESUBMITTAL - TI ALL | 09/20/2021 | COMPLETED |
| 09/14/2022 | REVISION - - 1ST | 09/14/2022 | ACTIVE |
| 09/27/2021 | RESUBMITTAL | 10/12/2021 | COMPLETED |
| 10/20/2021 | RESUBMITTAL | 10/21/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM03490
Permit Description: New Restaurant
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2021 | MECHANICAL - FINAL | PCAMARE1 | Approved | Air Balance Report required prior to Final Inspection |
| 02/15/2022 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
| 02/28/2022 | PLUMBING - PRE SLAB | DMUNIZ | Approved | Approved |
| 02/28/2022 | BUILDING PRE-SLAB | DMUNIZ | Approved | Approved |
| 03/23/2022 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved, water line to trash enclosure. |
| 03/23/2022 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
| 03/24/2022 | ROOF NAILING | DMUNIZ | Approved | Approved |
| 04/15/2022 | FIRE SPKLR - UG PIPING FLUSH | jfordney | Approved | |
| 04/15/2022 | FIRE SPKLR - UG PIPING FLUSH | jfordney | Approved | Cotractors test certificate |
| 04/19/2022 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | Approved. Clips and hold downs in place as per plans. |
| 04/19/2022 | FRAMING | JBURGE | Approved | Approved. Ok to insulate interior walls at site risk. |
| 04/22/2022 | PLUMBING - SEWER HCS CONNECT | TGAUSP | Approved | Approved, okay to backfill |
| 05/05/2022 | SHEET ROCK NAILING | DMUNIZ | Approved | APPROVED |
| 05/05/2022 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | Approved, Back corral ok to grout CMU |
| 05/19/2022 | STUCCO MESH | DMUNIZ | Approved | Approved |
| 05/31/2022 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
| 05/31/2022 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Approved, clear TEP ECO |
| 06/02/2022 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | not Applicable |
| 06/09/2022 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 06/09/2022 | MECHANICAL - PROGRESS | DMUNIZ | Approved | Approved |
| 06/09/2022 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Approved |
| 06/09/2022 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 06/09/2022 | U VALUE FOR WINDOW | DMUNIZ | Approved | Approved |
| 06/09/2022 | BUILDING - PROGRESS | DMUNIZ | Approved | Approved |
| 06/09/2022 | PLUMBING - PROGRESS | DMUNIZ | Approved | Approved |
| 06/09/2022 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Approved |
| 06/09/2022 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Approved Clear Southwest Gas. |
| 06/14/2022 | MECHANICAL - HOODS | DMUNIZ | Approved | Approved, smoke test PASS |
| 06/24/2022 | ELECTRIC - ABOVE CEILING | DMUINZ | Approved | Approved |
| 06/24/2022 | PLUMBING - ABOVE CEILING | DMUINZ | Approved | Approved |
| 06/24/2022 | MECHANICAL - ABOVE CEILING | DMUINZ | Approved | Approved |
| 07/06/2022 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | Approved |
| 07/06/2022 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | Approved |
| 07/06/2022 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | Not Applicable. |
| 07/06/2022 | MECHANICAL - HOOD SYSTEMS | DMUNIZ | Approved | Approved |
| 07/06/2022 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 07/11/2022 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
| 07/11/2022 | PLUMBING - FINAL | DMUNIZ | Approved | Approved |
| 07/14/2022 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
| 07/14/2022 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 07/14/2022 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 07/15/2022 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Approved |
| 07/15/2022 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Approved |
| 07/19/2022 | BUILDING - FINAL | DBENOIT | Approved | FINAL HEALTH DEPT PERMIT IN FILE |
| 07/21/2022 | FIRE - FINAL | CBASALDUA | Approved | |
| 07/25/2022 | ENGINEERING - FINAL | DROBERTS | Approved | Approved |