Permit: T21CM03394
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
7575 E SPEEDWAY BL
Address NEW:
7575 E SPEEDWAY BL
Apply Date:
04/22/2021
Applicant:
Description:
The project consists of a partial remodel to an existing fire station and a building addition
Permit Reviews
Permit Number - T21CM03394
Permit Status: Complete
Permit Description: The project consists of a partial remodel to an existing fire station and a building addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/11/2022 | REVISION - - 1ST | 03/17/2022 | COMPLETED |
| 04/07/2022 | REVISION - - 1ST | 04/11/2022 | COMPLETED |
| 04/22/2021 | COMMERCIAL - TI | 05/19/2021 | COMPLETED |
| 06/29/2021 | RESUBMITTAL | 07/22/2021 | COMPLETED |
| 11/24/2021 | RESUBMITTAL | 12/27/2021 | COMPLETED |
| 02/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/01/2023 | APPROVED |
Conditions
Permit Number - T21CM03394
Permit Status: Complete
Permit Description: The project consists of a partial remodel to an existing fire station and a building addition
| Date | Description | Comments |
|---|---|---|
| 07/13/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 07/13/2021 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
| 07/13/2021 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 07/13/2021 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 07/13/2021 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 07/13/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 07/13/2021 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 07/13/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 07/13/2021 | SPECIAL INSPECTION FOR SHOTCRETE IS REQUIRED. | |
| 07/13/2021 | WOOD I-JOISTS MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
| 03/01/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 07/13/2021 | NOTICE OF VIOLATION ISSUED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM03394
Permite Description: The project consists of a partial remodel to an existing fire station and a building addition
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
| 10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
| 04/24/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | N/A |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM03394
Permit Description: The project consists of a partial remodel to an existing fire station and a building addition
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/05/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 04/05/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/30/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Underground only.} | |
| 04/07/2022 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 04/07/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 04/06/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. 2nd lift.} ; {Activity date: 04/05/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval approved for 1st lift } |
|
| 04/20/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 04/20/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 06/20/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 06/20/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 07/01/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 07/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 03/30/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Underground only.} | |
| 07/01/2022 | COT - LCBU - Framing | Passed | {Activity date: 07/01/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 07/20/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 07/20/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 07/15/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval turn out gear room not complete} | |
| 09/14/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 09/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} | |
| 10/12/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE INCR} | |
| 10/12/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP. INCR clearance code for TEP. Called in at 1:46PM. } |
|
| 11/04/2022 | COT - LCME - Mechanical Progress | Passed | Final layer of wrap for kitchen hood. | |
| 11/23/2022 | COT - LCME - Mechanical Final | Passed | ||
| 11/23/2022 | COT - LCPL - Plumbing Final | Passed | ||
| 11/23/2022 | COT - LCEL - Electrical Final | Passed | ||
| 04/24/2023 | COT - FCON - Hood System - Final | Passed | ||
| 05/03/2023 | COT - FCON - Fire - Final | Passed | ||
| 04/24/2023 | COT - LCBU - Building Progress | Passed | ||
| 04/24/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 04/24/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | ||
| 04/24/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 04/24/2023 | COT - LCBU - Preslab | Passed | ||
| 04/28/2023 | COT - LCEL - Electrical Progress | Passed | ||
| 04/28/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 04/28/2023 | COT - LCEL - Service Upgrade | Passed | ||
| 04/28/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 04/28/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
| 04/28/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 04/28/2023 | COT - LCPL - Plumbing Progress | Passed | ||
| 04/28/2023 | COT - LCPL - Plumbing Roof Drains | Passed |