Permit: T21CM03232
Permit Details
Apply Date:
04/16/2021
Applicant:
Tucson Water
Description:
Equipping of new Tucson Water Well A-062A. The correct address for the site is 3670 W. Hardy Road.
Permit Reviews
Permit Number - T21CM03232
Permit Status: Complete
Permit Description: Equipping of new Tucson Water Well A-062A. The correct address for the site is 3670 W. Hardy Road.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/28/2021 | OTHER | 05/14/2021 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM03232
Permit Description: Equipping of new Tucson Water Well A-062A. The correct address for the site is 3670 W. Hardy Road.
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2022 | COT - LCBU - Preslab | Passed | {Activity date: 03/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 05/04/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 05/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap 3” from Trans to j box ok to backfill.} ; {Activity date: 04/22/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Conduits from new control bldg, to the well, From control bldg to flow control and chlorine bldg, From control bldg to power to pressure pedestal, Ktech and compressor. From control bldg to trans. All ok to backfill. } ; {Activity date: 04/06/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa 2-3” and 2-3/4” conduits from building, 150’ towards trans, ok to backfill.} ; {Activity date: 03/07/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa All under slab conduits in control building ok to drop matt’s.} |
|
| 10/13/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE ECO FOR COT WELL SITE ON W HARDY} | |
| 10/13/2022 | COT - LCEL - Construction Power | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Clear eco for COT well site on W Hardy Rd.} |
|
| 10/13/2022 | COT - LCEL - Temporary Service | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 01/26/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/26/2024 | COT - LCEL - Electrical Final | Passed | ||
| 01/26/2024 | COT - LCBU - Framing | Passed | ||
| 01/26/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
| 01/26/2024 | COT - LCBU - Building Progress | Passed | ||
| 01/26/2024 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 01/26/2024 | COT - LCBU - Masonry Pregrout | Passed | ||
| 01/26/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/26/2024 | COT - LCPL - Yard Water Line | Passed | ||
| 01/26/2024 | COT - LCME - Mechanical Final | Passed | ||
| 01/26/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 01/26/2024 | COT - LCBU - Building Final | Passed | ||
| 01/26/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 01/26/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 01/26/2024 | COT - LCEL - Outdoor Lighting | Passed |