Permit: T21CM03167
Permit Details
Apply Date:
04/14/2021
Applicant:
FORS Architecture
Description:
RESTAURANT
Architects:
- Sonya N. Sotinsky
Contractors:
- MW Morrissey
Permit Reviews
Permit Number - T21CM03167
Permit Status: C of o
Permit Description: RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/14/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/26/2021 | COMPLETED |
05/26/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 06/24/2021 | COMPLETED |
06/24/2021 | POST 3RD PARTY REVIEW | 07/13/2021 | COMPLETED |
08/31/2021 | REVISION - - 2ND | 12/01/2021 | COMPLETED |
12/02/2021 | REVISION - - 2ND | 12/17/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM03167
Permit Description: RESTAURANT
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/15/2021 | BUILDING PRE-SLAB | JBURGE | Approved | Approved |
07/15/2021 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | Approved |
07/15/2021 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Approved |
07/15/2021 | PLUMBING - PRE SLAB | JBURGE | Approved | Approved |
07/15/2021 | FIRE - KITCHEN EXH HOOD FINAL | IVR USER | Approved | IVRS - RI canceled |
07/15/2021 | FIRE - ALARM FINAL | IVR USER | Approved | IVRS - RI canceled |
07/15/2021 | FIRE SPKLR - FINAL | IVR USER | Approved | IVRS - RI canceled |
08/17/2021 | ELECTRIC - UNDERGROUND | JBURGE | Approved | Approved |
08/25/2021 | GAS CLEARANCE | DQUINN | Approved | CODE GAS |
08/25/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap Clear gas |
08/31/2021 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | Approved. |
10/01/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved |
10/01/2021 | PLUMBING - ABOVE CEILING | JBURGE | Approved | Approved |
10/01/2021 | SHEET ROCK NAILING | JBURGE | Approved | Approved |
10/01/2021 | FRAMING | JBURGE | Approved | Approved |
10/01/2021 | STEM WALL/RETAINING WALL | JBURGE | Approved | Approved |
10/08/2021 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Partial. Column footing for canopy area, Southwest ramp area. Ok to place concrete in progress areas |
10/08/2021 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Not ready. Contractor cancelled |
12/06/2021 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO |
12/06/2021 | BUILDING - PROGRESS | JBURGE | Approved | . Partial. Electric switch gear and panel #K-1 and section #1. Ok to set meter for SES Panel and energize section #1. CLEARANCE: Code: ECO |
12/22/2021 | MECHANICAL - PROGRESS | JBURGE | Approved | Not ready. Site locked. |
12/30/2021 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | Partial. Kitchen area. |
12/30/2021 | PLUMBING - PROGRESS | JBURGE | Approved | Partial. Kitchen area. |
12/30/2021 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | Partial. West panel in Kitchen area (100 amp) |
12/30/2021 | BUILDING ABOVE CEILING | JBURGE | Approved | Partial Kitchen area. |
12/30/2021 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | Approved |
01/05/2022 | ELECTRIC - PROGRESS | JBURGE | Approved | Approved |
01/05/2022 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | Approved |
01/05/2022 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved |
01/05/2022 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | Approved |
01/05/2022 | PLUMBING - GAS RECONNECT | JBURGE | Approved | Approved |
01/14/2022 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
01/14/2022 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved |
01/14/2022 | MECHANICAL - HOODS | ESTEVENS | Approved | Approved |
01/14/2022 | MECHANICAL - HOOD SYSTEMS | ESTEVENS | Approved | Approved |
01/14/2022 | FIRE - FINAL | wmotto1 | Approved | |
01/18/2022 | BUILDING - FINAL | JBURGE | Approved | Approved. Ok to make application for Certificate of Occupancy. |
01/18/2022 | MECHANICAL - FINAL | JBURGE | Approved | Approved. Air balance test results forwarded to Robert Sherry. |
01/18/2022 | PLUMBING - FINAL | JBURGE | Approved | Approved. Bacteria test results forwarded to Robert Sherry |
01/18/2022 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
02/24/2022 | ENGINEERING - FINAL | DROBERTS | Approved |