Permit: T21CM02898
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1015 E SILVERLAKE RD
Address NEW:
1015 E SILVERLAKE RD
Apply Date:
04/05/2021
Applicant:
Description:
New Wood Frame Office Building
Permit Reviews
Permit Number - T21CM02898
Permit Status: Complete
Permit Description: New Wood Frame Office Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/19/2022 | RESUBMITTAL | 02/02/2022 | COMPLETED |
| 04/05/2021 | COMMERCIAL - TI | 05/04/2021 | COMPLETED |
| 07/15/2021 | RESUBMITTAL | 09/02/2021 | COMPLETED |
| 12/07/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/14/2022 | APPROVED |
| 04/12/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/12/2023 | REQUIRES RESUBMIT |
| 04/20/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/02/2023 | APPROVED |
Conditions
Permit Number - T21CM02898
Permit Status: Complete
Permit Description: New Wood Frame Office Building
| Date | Description | Comments |
|---|---|---|
| 01/09/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
| 01/09/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM02898
Permit Description: New Wood Frame Office Building
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/28/2021 | COT - LCME - Mechanical Final | Passed | {Activity date: 07/28/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION} | |
| 07/28/2021 | COT - LCPL - Plumbing Final | Passed | {Activity date: 07/28/2021; Status: Prior to Final Inspectn; Inspector: LBOWERS; Comment: Entered by LBOWERS1 - WATER QUALITY REPORT REQUIRED PRIOR TO FINAL INSPECTION} | |
| 01/12/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/12/2023 | COT - HCBU - Preslab | Passed | ||
| 01/12/2023 | COT - HCEL - Electrical Underground | Passed | ||
| 01/26/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 01/26/2023 | COT - HCBU - Roof Nailing | Passed | ||
| 02/27/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
| 02/27/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 02/27/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 02/27/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 02/27/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 02/27/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
| 02/27/2023 | COT - HCBU - Framing | Passed | ||
| 03/13/2023 | COT - HCPL - Yard Water Line | Passed | ||
| 03/13/2023 | COT - HCPL - Sewer | Passed | ||
| 05/09/2023 | BULD - Electrical Clearance | Passed | Approved new service, ECO Clearance to TEP required for 1015 E Silverlake Rd | |
| 08/02/2023 | COT - HCPL - Plumbing Progress | Passed | ||
| 08/02/2023 | COT - HCME - Mechanical Progress | Passed | ||
| 08/02/2023 | COT - HCEL - Electrical Progress | Passed | ||
| 08/03/2023 | COT - HCEL - Outdoor Lighting | Passed | ||
| 08/02/2023 | COT - HCPL - Rough Soil | Passed | ||
| 08/03/2023 | COT - HCEL - Electrical Final | Passed | ||
| 08/03/2023 | COT - HCME - Mechanical Final | Passed | ||
| 08/03/2023 | COT - HCPL - Plumbing Final | Passed | ||
| 08/03/2023 | COT - HCBU - Building Progress | Passed | ||
| 08/03/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
| 08/03/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 08/04/2023 | COT - HCBU - Building Final | Passed | ||
| 09/20/2023 | ENGR Engineering Final | Passed | ||
| 09/25/2023 | COT - FCON - Fire - Final | Passed |