Permit: T21CM02179
Permit Details
Apply Date:
03/10/2021
Applicant:
Tucson Expediting & Development
Description:
Medical Office
Architects:
- Douglas Robidoux
Contractors:
- BRYCOR BUILDERS L L C
Permit Reviews
Permit Number - T21CM02179
Permit Status: C of o
Permit Description: Medical Office
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/10/2021 | COMMERCIAL - TI | 04/13/2021 | COMPLETED |
| 04/21/2021 | RESUBMITTAL | 05/10/2021 | COMPLETED |
| 05/13/2021 | RESUBMITTAL | 05/17/2021 | COMPLETED |
| 05/18/2021 | RESUBMITTAL | 05/19/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM02179
Permit Description: Medical Office
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/21/2021 | PLUMBING - ROUGH, SOIL | RELEFANTE | Approved | |
| 08/03/2021 | TEP CLEARANCE - PM | TGAUSP | Approved | CODE INCR |
| 08/03/2021 | REINFORCED MASONRY PRE-GROUT | TGAUSP | Approved | Approved for 3 door openings |
| 08/03/2021 | ELECTRIC - SERVICE UPGRADE | TGAUSP | Approved | Approved for 800A, please send INCR Clearance to TEP |
| 08/11/2021 | ELECTRIC - INTERMEDIATE | RELEFANTE | Approved | AP |
| 08/11/2021 | PLUMBING - INTERMEDIATE | RELEFANTE | Approved | AP |
| 08/11/2021 | MECHANICAL - INTERMEDIATE | RELEFANTE | Approved | AP |
| 08/19/2021 | TEP CLEARANCE - AM | RELEFANTE | Approved | CODE INCR/ PANEL M1 |
| 08/26/2021 | ELECTRIC - PROGRESS | RELEFANTE | Approved | AP |
| 10/04/2021 | BUILDING PRE-SLAB | DQUINN | Approved | Ap |
| 10/04/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ap |
| 10/04/2021 | ELECTRIC - UFER | DQUINN | Approved | Ap |
| 10/04/2021 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | na |
| 10/04/2021 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Ap |
| 10/27/2021 | GAS CLEARANCE | DQUINN | Approved | CODE GAS |
| 10/27/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap Clear gas |
| 11/18/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | na |
| 11/18/2021 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | na |
| 11/18/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | na |
| 11/18/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 11/18/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 11/18/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 11/18/2021 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
| 11/18/2021 | BUILDING ABOVE CEILING | DQUINN | Approved | Ap |
| 11/18/2021 | FRAMING | DQUINN | Approved | Ap |
| 11/24/2021 | CERTIFICATE OF OCCUPANCY | aquiroz | Approved | |
| 11/24/2021 | BUILDING - FINAL | aquiroz | Approved | |
| 11/24/2021 | FIRE - FINAL | CBASALDUA | Approved | |
| 11/24/2021 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 11/24/2021 | FIRE SPKLR - FINAL | CBASALDUA | Approved |