Permit: T21CM01941
Permit Details
Apply Date:
03/04/2021
Applicant:
Troy White
Description:
DRIVE THROUGH COFFEE SHOP
Architects:
- Wayne Swan
Contractors:
- Pate Contractors llc
Permit Reviews
Permit Number - T21CM01941
Permit Status: C of o
Permit Description: DRIVE THROUGH COFFEE SHOP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/04/2021 | COMMERCIAL - NEW | 04/22/2021 | COMPLETED |
04/22/2021 | RESUBMITTAL | 05/21/2021 | COMPLETED |
06/18/2021 | REVISION - - 1ST | 06/29/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM01941
Permit Description: DRIVE THROUGH COFFEE SHOP
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2021 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
07/09/2021 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | UNDER SLAB ONLY |
07/21/2021 | PLUMBING - PROGRESS | RELEFANTE | Approved | |
07/21/2021 | PLUMBING - INTERMEDIATE | RELEFANTE | Approved | |
07/21/2021 | PLUMBING - PRE SLAB | RELEFANTE | Approved | |
07/21/2021 | ELECTRIC - UFER | RELEFANTE | Approved | |
07/21/2021 | BUILDING PRE-SLAB | RELEFANTE | Approved | |
07/21/2021 | EXCAVATION/LAYOUT REBAR & ZON | RELEFANTE | Approved | |
07/29/2021 | BUILDING - PROGRESS | RELEFANTE | Approved | AP |
08/06/2021 | ROOF NAILING | RCHANDLER | Approved | -AP |
08/11/2021 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | Approved |
08/11/2021 | FRAMING | WGALLAGHER | Approved | Approved |
08/20/2021 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | NA |
08/20/2021 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | AP. OK to insulate. |
08/20/2021 | MECHANICAL - PROGRESS | RCHANDLER | Approved | AP OK to insulate 10:30 field 8:34: sent text with 10-12 ETA |
08/20/2021 | MECHANICAL - ABOVE CEILING | RCHANDLER | Approved | AP OK to insulate |
08/20/2021 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | AP OK to insulate |
08/20/2021 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | AP OK to insulate |
08/20/2021 | ELECTRIC - PROGRESS | RCHANDLER | Approved | AP OK to insulate |
08/20/2021 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | AP OK to insulate |
09/03/2021 | SHEET ROCK NAILING | RCHANDLER | Approved | AP |
10/12/2021 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | AP |
11/03/2021 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | Approved |
12/01/2021 | TEP CLEARANCE - PM | TLUNDBERG | Approved | CODE ECO |
12/01/2021 | ELECTRIC - SERVICE UPGRADE | TLUNDBERG | Approved | AP TEP ECO |
12/22/2021 | ELECTRIC - ABOVE CEILING | TLUNDBERG | Approved | AP |
12/27/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
01/06/2022 | FIRE - FINAL | jfordney | Approved | |
01/06/2022 | BUILDING ABOVE CEILING | ESTEVENS | Approved | Approved |
01/10/2022 | PLUMBING - FINAL | ESTEVENS | Approved | Approved 1090 |
01/10/2022 | ELECTRIC - FINAL | ESTEVENS | Approved | Approved |
01/10/2022 | BUILDING - FINAL | ESTEVENS | Approved | Approved |
01/10/2022 | HEALTH DEPT - FINAL 724-7908 | JG3 | Approved | PC Health Approval received 1/10/2022 |