Permit: T21CM01625
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
1697 S SAN ANTONIO DR
Address NEW:
1697 S SAN ANTONIO DR
Apply Date:
02/23/2021
Applicant:
RAMON VALDEZ
Description:
SFR VALD000119 T19-M003
Contractors:
- VAL VAL CONSTRUCTION LLC
Permit Reviews
Permit Number - T21CM01625
Permit Status: C of o
Permit Description: SFR VALD000119 T19-M003
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/25/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/24/2021 | COMPLETED |
| 03/26/2021 | RESUBMITTAL | 04/16/2021 | COMPLETED |
| 07/15/2021 | REVISION - - 1ST | 07/15/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM01625
Permit Status: C of o
Permit Description: SFR VALD000119 T19-M003
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/23/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM01625
Permit Description: SFR VALD000119 T19-M003
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/22/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | |
| 04/22/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 04/27/2021 | ELECTRIC - UFER | TGAUSP | Approved | |
| 04/27/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | APPROVED, OK TO POUR |
| 04/27/2021 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | |
| 05/14/2021 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | APPROVED AND OK TO BACKFILL - NOTE FOR FUTURE LOT SPLIT 3-1 INCH PE WATER LINES FROM METER THROUGH UTILITY EASEMENT TO THE 3 PARTIALS |
| 05/14/2021 | PLUMBING - YARD WTR LINE/TEST | TGAUSP | Approved | Approved and okay to backfill. *Note for future lot split: 3-1” PE waterlines from meter through utility easement to 3 parcels. |
| 05/24/2021 | ROOF NAILING | TGAUSP | Approved | APPROVED OK TO ROOF |
| 05/24/2021 | EXT METAL CLIPS/EXT SHEATHING | TGAUSP | Approved | APPROVED OK TO FOAM/LATH |
| 05/26/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | CODE ECO |
| 05/26/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 05/26/2021 | FRAMING | DQUINN | Approved | |
| 05/26/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 05/26/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 05/26/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | |
| 05/26/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 06/02/2021 | TEP CLEARANCE - AM | DQUINN | Approved | CODE ECO |
| 08/06/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Na |
| 08/06/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 08/06/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap |
| 08/06/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 08/06/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 08/10/2021 | BUILDING - FINAL | DQUINN | Approved |