Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM01556
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
12957 E PANTANO VIEW DR
Address NEW:
12957 E PANTANO VIEW DR
Apply Date:
02/22/2021
Applicant:
Description:
SFR LENN350419 T19-M0169
Outstanding Activity Conditions
Permit Number - T21CM01556
Permit Status: Expired
Permit Description: SFR LENN350419 T19-M0169
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 02/22/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 02/22/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 02/22/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T21CM01556
Permite Description: SFR LENN350419 T19-M0169
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM01556
Permit Description: SFR LENN350419 T19-M0169
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 03/11/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
| 03/11/2021 | COT - RSPL - Sewer | Passed | {Activity date: 03/11/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
| 03/11/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 03/11/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
| 03/23/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 03/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 03/23/2021 | COT - RSBU - Preslab | Passed | {Activity date: 03/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 03/23/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 03/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 03/23/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 03/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 04/27/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 04/27/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 04/27/2021 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 04/27/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 08/27/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/27/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
| 08/27/2021 | COT - LCBU - Framing | Passed | {Activity date: 08/27/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
| 08/27/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 08/27/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
| 08/27/2021 | RSME - Mechanical Progress | Passed | {Activity date: 08/27/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved} | |
| 08/27/2021 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/27/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved, no clearance, no valves} | |
| 09/08/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/08/2021; Status: Approved; Inspector: WGALLGHER; Comment: Entered by RSALDAT1 - Approved} | |
| 11/10/2021 | COT - RSEL - Construction Power | Passed | {Activity date: 11/10/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP TEP ECO } ; {Activity date: 11/05/2021; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - CO. Instal metal address label on panel door.} |
|
| 11/10/2021 | BULD - Electrical Clearance | Passed | {Activity date: 11/10/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - CODE ECO} | |
| 11/22/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 11/22/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP} | |
| 11/22/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 11/22/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - AP SWG CLEARANCE REQUIRED} |
|
| 11/22/2021 | COT - BULD - SWG Clearance | Passed | {Activity date: 11/22/2021; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by RSALDAT1 - CODE} | |
| 12/16/2021 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 12/16/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 12/16/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 12/16/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} |