Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM01312
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3139 E BELLEVUE ST BLDG 2
Address NEW:
3139 E BELLEVUE ST BLDG 2
Apply Date:
02/16/2021
Applicant:
Ginger Schaad
Description:
New Apartment Building #2
Permit Reviews
Permit Number - T21CM01312
Permit Status: Complete
Permit Description: New Apartment Building #2
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/04/2022 | RESUBMITTAL | 03/02/2022 | COMPLETED |
| 02/16/2021 | COMMERCIAL - NEW | 04/02/2021 | COMPLETED |
| 10/13/2021 | RESUBMITTAL | 11/08/2021 | COMPLETED |
| 12/02/2021 | RESUBMITTAL | 12/17/2021 | COMPLETED |
| 06/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/21/2023 | APPROVED |
| 10/04/2024 | COMMERCIAL REVIEW - FULL v.2 | 10/11/2024 | APPROVED |
| 07/22/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/23/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - T21CM01312
Permit Status: Complete
Permit Description: New Apartment Building #2
| Date | Description | Comments |
|---|---|---|
| 05/10/2023 | Contractor's active Arizona Contractor's License number for specified scope of work required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM01312
Permite Description: New Apartment Building #2
Total Outstanding Inspections - 25
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2022 | COT - LCBU - Building Above Ceiling | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Plumbing Progress | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Construction Power | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Underground Flush | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Alarm - Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Sprinkler - Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Sustainability | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | FCON – OH Piping & Hydro | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Building Progress | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Underground Pressure | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Medical Gas/Test | N/A | Canceled | Inspection Canceled |
| 08/10/2023 | COT - LCBU - Roof Nailing | N/A | Partial Pass | Building Two. |
| 11/13/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | Third Floor. 11/13/23: mechanical intermediate passed. |
| 11/13/2023 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 10/19/23 partial approval for drywall in areas where air handlers are located, ok to place ceiling cassette air handlers in all units 11/13/23: ok to tape and mud 6 unit apartment complex. |
| 07/09/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 08/10/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | Building Two. |
| 08/10/2023 | COT - LCBU - Framing | N/A | Not Ready | Wanted consultation. |
| 05/07/2024 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | 5/7/24: this is a dumpster enclosure inspection need engineering inspection |
| 11/13/2023 | COT - LCEL - Electrical Progress | N/A | Partial Pass | 11/13/23: drop ceiling hard lids electrical per plan ok to proceed in 6 unit complex |
| 07/09/2024 | COT - LCPL - Gas Pressure Test | N/A | Not Applicable | |
| 08/30/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | 8/30/23: not ready for inspection. |
| 08/30/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Ready | 8/30/23: not ready for inspection. |
| 07/11/2023 | COT - LCPL - Rough Soil | N/A | Canceled |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM01312
Permit Description: New Apartment Building #2
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2023 | COT - LCPL - Sewer | Passed | Ok to cover progress areas | |
| 06/30/2023 | COT - LCBU - Preslab | Passed | ||
| 06/30/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 07/11/2023 | COT - HCBU - Preslab | Passed | ||
| 10/02/2023 | COT - LCPL - Plumbing Intermediate | Passed | 10-2-23: Walls are dried in, windows are installed, styrofoam and wire for stucco is installed. Electrical and plumbing rough-in is complete on Building #2. Okay to proceed with insulation and drywall. | |
| 10/02/2023 | COT - LCEL - Electrical Intermediate | Passed | 10-2-23: Walls are dried in, windows are installed, styrofoam and wire for stucco is installed. Electrical and plumbing rough-in is complete on Building #2. Okay to proceed with insulation and drywall. | |
| 10/11/2023 | COT - LCME - Mechanical Progress | Passed | ||
| 06/26/2024 | BULD - Electrical Clearance | Passed | ||
| 07/03/2024 | COT - LCPL - Backwater Valve | Passed | ||
| 07/09/2024 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 07/09/2024 | COT - LCBU - Framing | Passed | ||
| 07/09/2024 | COT - LCBU - Masonry Pregrout | Passed | ||
| 07/09/2024 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
| 07/09/2024 | COT - LCEL - Electrical Progress | Passed | ||
| 07/09/2024 | COT - LCEL - Electrical Underground | Passed | ||
| 07/09/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
| 07/09/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
| 07/09/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 07/09/2024 | COT - LCPL - Plumbing Roof Drains | Passed | ||
| 07/19/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 07/19/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 07/22/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 07/25/2024 | COT - HCBU - TCO | Passed | ||
| 12/24/2024 | COT - FCON - Fire - Final | Passed | ||
| 12/24/2024 | COT - LCBU - Building Final | Passed | Building final for building #1 is contingent on building #2 passing final. | |
| 12/24/2024 | COT - LCEL - Electrical Final | Passed | ||
| 12/24/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 12/24/2024 | COT - LCME - Mechanical Final | Passed | ||
| 12/24/2024 | ENGR Engineering Final | Passed |