Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Address:
260 S CHURCH AV
Apply Date:
02/12/2021
Applicant:
Description:
TCC new meeting room addition - TCO issued for levels 1, 2 and imediate exterior. 4/7/2022

Permit Reviews

Permit Number - T21CM01283
Permit Status: Issued
Permit Description: TCC new meeting room addition - TCO issued for levels 1, 2 and imediate exterior. 4/7/2022
Start Date Submittal Complete Date Status  
02/12/2021 COMMERCIAL - NEW 04/19/2021 COMPLETED Review Details
04/19/2021 RESUBMITTAL - TI ALL 05/20/2021 COMPLETED Review Details
06/16/2021 RESUBMITTAL - TI ALL 07/14/2021 COMPLETED Review Details
08/16/2021 REVISION - - 1ST 08/26/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T21CM01283
Permit Status: Issued
Permit Description: TCC new meeting room addition - TCO issued for levels 1, 2 and imediate exterior. 4/7/2022
Total Outstanding Activity Conditions - 11
Date Name
03/03/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
03/03/2021 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
03/03/2021 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
03/03/2021 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
03/03/2021 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM01283
Permite Description: TCC new meeting room addition - TCO issued for levels 1, 2 and imediate exterior. 4/7/2022
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
11/07/2022 COT - LCBU - Building Final N/A Canceled Inspection Canceled
11/07/2022 COT - LCME - Mechanical Final N/A Canceled Inspection Canceled
11/07/2022 COT - FCON - Alarm - Final N/A Canceled Inspection Canceled
11/07/2022 COT - FCON - Sprinkler - Final N/A Canceled Inspection Canceled
11/07/2022 COT - FCON - Fire - Final N/A Canceled Inspection Canceled
11/07/2022 COT - LCPL - Plumbing Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Issued
Permit Number: T21CM01283
Permit Description: TCC new meeting room addition - TCO issued for levels 1, 2 and imediate exterior. 4/7/2022
Total Completed Inspections - 29
Date Description Inspector Results Comments
02/01/2022 COT - LCPL - Gas Pressure Test Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Stem Wall/Retaining Wall Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Framing Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Electrical Underground Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - } ; {Activity date: 04/19/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. West wall rebar at GL: DD/20.7-19.2 at 6’6”-15’6”} ; {Activity date: 04/15/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Retaining wall at GL: BB-Z.4/19; forms set, Ok to place concrete.} ; {Activity date: 04/13/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Elevator #2 (East Elevator); slab footing. Ok to place concrete.} ; {Activity date: 04/12/2021; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Not ready. Contractor cancelled will reschedule East Elevator footings for 13 April.} ; {Activity date: 04/09/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Partial. Grade beams and footings at CRW5; CRW3; CRW2. Ok to place concrete in progress areas.

}
02/01/2022 COT - LCBU - Firewall/Fire Barrier/Firestop Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Construction Power Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCPL - Plumbing Roof Drains Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Outdoor Lighting Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Preslab Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Electrical Final Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - HCBU - Exterior Clips/Sheathing Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Sustainability Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Temporary Service Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCPL - Rough Soil Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Roof Nailing Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 FCON – OH Piping & Hydro Passed {Activity date: 02/01/2022; Status: Approved; Inspector: wmotto1; Comment: Entered by WMOTTO1 - }
02/01/2022 COT - LCPL - Yard Water Line Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCPL - Sewer Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - CofO Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
02/01/2022 COT - LCBU - Masonry Pregrout Passed {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
07/18/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 07/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - } ; {Activity date: 02/15/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by RSALDAT1 - . Not ready. Contractor cancelled. Will reschedule for 16 February.} ; {Activity date: 02/11/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Level #2; Exhibition areas. Ok to set ceiling tiles on border areas and special cut areas.} ; {Activity date: 02/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - }
07/18/2022 COT - LCBU - Building Progress Passed {Activity date: 07/18/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - } ; {Activity date: 04/07/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Levels #1 and #2 and end exterior portion of project. Ok to make application for Temporary Certificate of Occupancy for current project.

} ; {Activity date: 04/06/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - . Partial. Pre-TCO walk through for levels 1 &2.} ; {Activity date: 03/30/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Corrections for ADA Level #1 men’s restroom are complete.

} ; {Activity date: 03/01/2022; Status: Not ready for Inspection; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Not ready. ADA issue in level #1 restroom. Will reschedule for 2 March.} ; {Activity date: 02/01/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by RSALDAT1 - } ; {Activity date: 02/01/2022; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Up date for permit.}

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
T21CM01283 - TCO LEVELS1 2.PDF DOCUMENTS VIEW
T21CM01283 - TCO 1ST FLOOR ONLY.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
REVISION NARRATIVE.PDF DOCUMENTS VIEW
SIC FINAL.PDF DOCUMENTS VIEW
PLAN SET REV1.PDF DOCUMENTS VIEW
COMCHECK.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
HVAC CALCS.PDF DOCUMENTS VIEW
GEOTECH REPORT.PDF DOCUMENTS VIEW
LANDSCAPE SPECIFICATIONS.PDF DOCUMENTS VIEW
TECHNICAL SPECIFICATIONS.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
OUTDOOR LIGHTING CODE CALCS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW