Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
02/11/2021
Applicant:
Description:
3 existing building remodels and 1 new building addition to a former abandoned commercial office add

Permit Reviews

Permit Number - T21CM01250
Permit Status: Complete
Permit Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Start Date Submittal Complete Date Status  
02/11/2021 COMMERCIAL - TI 04/26/2021 COMPLETED Review Details
04/26/2021 RESUBMITTAL 05/24/2021 COMPLETED Review Details
05/25/2021 RESUBMITTAL 09/20/2021 COMPLETED Review Details
12/08/2022 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/03/2023 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM01250
Permite Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
12/08/2022 COT - FCON - Sprinkler - Final N/A Partial Pass Alarm not installed yet, sprinkler system not being monitored
12/08/2022 COT - LCME - Mechanical Final N/A Partial Pass All but balance report.
COT - FCON - Fire - Final N/A Not Ready
01/10/2023 COT - LCBU - Building Final N/A Partial Pass Permanent electrical parts for service needed; balance complete. Recommend issuing TCO.

Completed Inspections

Permit Status: Complete
Permit Number: T21CM01250
Permit Description: 3 existing building remodels and 1 new building addition to a former abandoned commercial office add
Total Completed Inspections - 23
Date Description Inspector Results Comments
12/15/2021 COT - LCPL - Plumbing Progress Passed {Activity date: 12/15/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/20/2021; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Pre-Slab.}
01/06/2022 COT - LCPL - Gas Pressure Test Passed {Activity date: 01/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
01/06/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 01/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/16/2021; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Underground plumbing.}
01/06/2022 COT - LCPL - Plumbing Above Ceiling Passed {Activity date: 01/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP}
01/19/2022 COT - LCPL - Yard Water Line Passed {Activity date: 01/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP

Field

12-2

Texted ETA at 10:00}
03/01/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 03/01/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
03/01/2022 COT - LCBU - Framing Passed {Activity date: 03/01/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved}
08/03/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 08/03/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 07/21/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Apartment.} ; {Activity date: 05/18/2022; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by VVERA1 - CA}
08/30/2022 COT - LCEL - Electrical Progress Passed {Activity date: 08/30/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved. ECO clearance for TEP; one meter in new switchgear.

} ; {Activity date: 02/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Electric Rough in and UG.

Field

10-12

Texted ETA at 8:16} ; {Activity date: 01/19/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -DE. Walls only. 1-Land all wire assemblies in walls. 2-Bond water piping.}
08/30/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 08/30/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - CODE ECO}
09/21/2022 COT - LCBU - Building Progress Passed {Activity date: 09/21/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP. Gas pressure test; Clearance with future inspection.} ; {Activity date: 03/21/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Pre-grout for courtyard walls.} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. 1st lift of site wall between buildings 1and 2.

EAP

Mike wants early as possible}
10/06/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 10/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. All but suspended ceilings.} ; {Activity date: 03/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Hard lids.} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. OK to sheet rock hard lid areas}
10/06/2022 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 10/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP. Including Plumbing.} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. All but suspended ceilings.} ; {Activity date: 03/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - PA. Hard lids.

Field

12-2} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. OK to sheet rock hard lid areas}
10/06/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 10/06/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. All but suspended ceilings.} ; {Activity date: 03/10/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -PA. Hard lids.} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. OK to sheet rock hard lid areas}
12/08/2022 COT - LCME - Mechanical Progress Passed
12/08/2022 COT - LCME - Mechanical Intermediate Passed
12/08/2022 COT - LCEL - Electrical Final Passed
01/05/2023 COT - FCON - Alarm - Final Passed OK to obtain TCO.
01/06/2023 COT - LCME - Mechanical Final Passed
01/06/2023 COT - LCPL - Plumbing Final Passed
01/11/2023 COT - FCON - Fire - Final Passed OK to obtain TCO.
01/10/2023 COT - LCEL - Outdoor Lighting Passed
09/18/2023 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
T21CM01250 TCO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
21-019 TEST - BALANCE REPORT A,B,C - D_V1.PDF DOCUMENTS VIEW
21-019 WATER CHLORINATION REPORT ABC-D_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
HEATING & COOLING LOAD CALCULATIONS.PDF DOCUMENTS VIEW
COM CHECK BUILDING A.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW