Permit Details

Status:
Final
Type:
COMMERCIAL ALTERATION
Address NEW:
750 N ALVERNON WY
Apply Date:
02/10/2021
Applicant:
Comprehensive Risk Service LLc
Description:
Fire Damage Repair
Architects:
  • David McGuire
Contractors:
  • Comprehensive Risk Services

Completed Inspections

Permit Status: Final
Permit Number: T21CM01219
Permit Description: Fire Damage Repair
Total Completed Inspections - 12
Date Description Inspector Results Comments
03/22/2021 TEP CLEARANCE - PM DMUNIZ Approved CODE RECN/ Temp power installed from main switchgear to Temporary Broiler
04/27/2021 FRAMING RELEFANTE Approved
05/13/2021 MECHANICAL - ABOVE CEILING ESTEVENS Approved
05/13/2021 ELECTRIC - ABOVE CEILING ESTEVENS Approved
05/13/2021 PLUMBING - FINAL ESTEVENS Approved
05/20/2021 MECHANICAL - FINAL TTREMBULAK Approved
05/20/2021 MECHANICAL - PROGRESS TTREMBULAK Approved
05/20/2021 PLUMBING - PROGRESS TTREMBULAK Approved
05/20/2021 ELECTRIC - FINAL TTREMBULAK Approved
05/20/2021 ELECTRIC - PROGRESS TTREMBULAK Approved
05/20/2021 BUILDING - FINAL TTREMBULAK Approved
05/20/2021 BUILDING - PROGRESS TTREMBULAK Approved

Documents

File Name Document Type  
09-21-01.3 MAR 11 INSPECTION - BANNER SURGERY CENTER - 750 N ALVERNON WAY 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
09-21-01.3 MAR 11 INSPECTION - BANNER SURGERY CENTER - 750 N ALVERNON WAY.PDF DOCUMENTS VIEW