Permit: T21CM01198
Permit Details
Apply Date:
02/10/2021
Applicant:
JR Durazo
Description:
New: Restroom (Building B)
Permit Reviews
Permit Number - T21CM01198
Permit Status: Complete
Permit Description: New: Restroom (Building B)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/10/2021 | COMMERCIAL - NEW | 03/22/2021 | COMPLETED |
04/12/2021 | RESUBMITTAL | 05/10/2021 | COMPLETED |
06/10/2022 | REVISION - - 2ND | 06/24/2022 | COMPLETED |
12/21/2021 | REVISION - - 1ST | 02/17/2022 | COMPLETED |
10/31/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/02/2023 | APPROVED |
05/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/24/2023 | APPROVED |
Conditions
Permit Number - T21CM01198
Permit Status: Complete
Permit Description: New: Restroom (Building B)
Date | Description | Comments |
---|---|---|
06/23/2022 | SHOP DRAWINGS REQUIRED FOR TRUSS | |
11/02/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
11/02/2023 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
11/02/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM01198
Permite Description: New: Restroom (Building B)
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/31/2023 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | East side of building, sidewalk. |
10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Sewer | N/A | Not Ready | |
05/22/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM01198
Permit Description: New: Restroom (Building B)
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2022 | COT - LCPL - Yard Water Line | Passed | {Activity date: 06/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
07/01/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 07/01/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to cover} | |
07/14/2022 | COT - LCBU - Preslab | Passed | {Activity date: 07/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for building B} | |
07/14/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 07/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for building B} ; {Activity date: 07/01/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR} | |
08/19/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
08/30/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 08/30/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
10/03/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Approved. Building B.} ; {Activity date: 08/19/2022; Status: Partial Approval; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - partial. Waiting on Metal stud framing.} | |
10/17/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/17/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/17/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 10/03/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready. Boxes need to be made up. Missing ground screws. Building B. } |
|
02/13/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | stem wall footing is good. Okay to pour concrete. | |
05/22/2023 | COT - LCBU - Masonry Pregrout | Passed | ||
05/22/2023 | COT - LCME - Mechanical Final | Passed | ||
05/22/2023 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
05/22/2023 | COT - LCEL - Electrical Underground | Passed | ||
05/22/2023 | COT - LCPL - Plumbing Final | Passed | ||
05/22/2023 | COT - LCPL - Sewer | Passed | ||
05/22/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
05/22/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
05/22/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
05/22/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
05/22/2023 | COT - FCON - Alarm - Final | Passed | Building does not have a Fire Alarm. | |
05/23/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
05/22/2023 | COT - LCME - Mechanical Underground | Passed | ||
05/22/2023 | COT - FCON - Sprinkler - Final | Passed | Not a sprinklered building | |
05/22/2023 | COT - FCON - Fire - Final | Passed | ||
05/22/2023 | COT - LCBU - Building Progress | Passed | ||
05/22/2023 | COT - LCPL - Gas Pressure Test | Passed | ||
10/13/2023 | COT - LCEL - Electrical Final | Passed | ||
01/19/2024 | ENGR Engineering Final | Passed | ||
01/19/2024 | PDSD Building Division - Sign Final | Passed | ||
01/19/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
02/21/2024 | COT - LCBU - Building Final | Passed |