Permit: T21CM01109
Permit Details
Apply Date:
02/08/2021
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHOH35B19 T19-M0140
Contractors:
- D R H TUCSON CONSTRUCTION
Outstanding Activity Conditions
Permit Number - T21CM01109
Permit Status: Final
Permit Description: SFR DRHOH35B19 T19-M0140
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/08/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T21CM01109
Permit Description: SFR DRHOH35B19 T19-M0140
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/10/2021 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | APPROVED |
02/10/2021 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | APPROVED |
02/10/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | APPROVED |
02/16/2021 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
02/16/2021 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | APPROVED |
02/16/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | APPROVED |
02/16/2021 | ELECTRIC - UFER | DQUINN | Approved | APPROVED |
02/16/2021 | BUILDING PRE-SLAB | DQUINN | Approved | APPROVED |
02/16/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | APPROVED |
03/05/2021 | ROOF NAILING | DQUINN | Approved | |
03/05/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
04/09/2021 | GAS CLEARANCE | DQUINN | Approved | CODE |
04/09/2021 | FRAMING | DQUINN | Approved | Ap |
04/09/2021 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | Ap |
04/09/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Ap |
04/09/2021 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap |
04/09/2021 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | Ap |
04/21/2021 | SHEET ROCK NAILING | DQUINN | Approved | |
05/26/2021 | MECHANICAL - FINAL | DQUINN | Approved | |
05/26/2021 | PLUMBING - FINAL | DQUINN | Approved | |
05/26/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
05/26/2021 | ELECTRIC - FINAL | DQUINN | Approved | |
05/26/2021 | BUILDING - FINAL | DQUINN | Approved |