Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Commercial Building
Address:
1545 E COPPER ST
Address NEW:
1545 E COPPER ST
Apply Date:
02/04/2021
Applicant:
Ernie Duarte
Description:
Installation of poles and electrical systems for stadium lighting

Permit Reviews

Permit Number - T21CM01063
Permit Status: Expired
Permit Description: Installation of poles and electrical systems for stadium lighting
Start Date Submittal Complete Date Status  
02/05/2021 OTHER 02/18/2021 COMPLETED Review Details
03/31/2021 REVISION - - 1ST 04/20/2021 COMPLETED Review Details
04/21/2021 REVISION - - 1ST 04/28/2021 COMPLETED Review Details

Outstanding Inspections

Permit Status: Expired
Permit Number: T21CM01063
Permite Description: Installation of poles and electrical systems for stadium lighting
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
05/20/2021 COT - LCBU - Preslab N/A Canceled {Activity date: 05/20/2021; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by VLEON1 - }
05/20/2021 COT - LCPL - Plumbing Intermediate N/A Canceled {Activity date: 05/20/2021; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by VLEON1 - }
11/07/2022 COT - LCBU - Building Final N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T21CM01063
Permit Description: Installation of poles and electrical systems for stadium lighting
Total Completed Inspections - 7
Date Description Inspector Results Comments
03/24/2021 COT - LCEL - Electrical Underground Passed {Activity date: 03/24/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa
Underground from north goalpost, west and south to 2 light poles,completing F1 F2. Ok to backfill.

} ; {Activity date: 03/18/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VLEON1 - PARTIAL - Trench continues on east side to pole and then to concession stand. Ok to backfill.

}
04/05/2021 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 04/05/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap}
04/05/2021 COT - LCEL - Grounding/Bonding Passed {Activity date: 04/05/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap
16’ deep footings and grounding ok to pour - F1, F2, F3, F4 light bases on football field}
05/20/2021 COT - LCEL - Electrical Intermediate Passed {Activity date: 05/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - Stadium lighting, distribution conduits to and from panels, to east and west concessions and press box switches and outlets ok for use.}
05/20/2021 COT - LCEL - Outdoor Lighting Passed {Activity date: 05/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - Stadium lighting, distribution conduits to and from panels, to east and west concessions and press box switches and outlets ok for use.}
05/20/2021 COT - LCEL - Electrical Final Passed {Activity date: 05/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - Stadium lighting, distribution conduits to and from panels, to east and west concessions and press box switches and outlets ok for use.}
05/20/2021 COT - LCPL - Plumbing Final Passed {Activity date: 05/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - }