Permit Details

Status:
Issued
Type:
Commercial Building
Address:
9800 E RITA RD
Address NEW:
9800 E RITA RD
Apply Date:
02/02/2021
Applicant:
Lisa Bowers
Description:
New splash pad with plumbing, electrical

Permit Reviews

Permit Number - T21CM01036
Permit Status: Issued
Permit Description: New splash pad with plumbing, electrical
Start Date Submittal Complete Date Status  
02/03/2021 OTHER 03/04/2021 COMPLETED Review Details
02/10/2022 REVISION - - 1ST 02/17/2022 COMPLETED Review Details
12/02/2021 RESUBMITTAL 12/17/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T21CM01036
Permit Status: Issued
Permit Description: New splash pad with plumbing, electrical
Total Outstanding Activity Conditions - 4
Date Name
02/23/2021 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
02/23/2021 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
02/23/2021 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/23/2021 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM01036
Permite Description: New splash pad with plumbing, electrical
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - ENGR - Site - Assurance Release N/A Not Ready
10/27/2022 COT - LCBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T21CM01036
Permit Description: New splash pad with plumbing, electrical
Total Completed Inspections - 12
Date Description Inspector Results Comments
10/18/2021 COT - LCEL - Electrical Underground Passed {Activity date: 10/18/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved OK to cover secondary line

}
02/14/2022 COT - LCBU - Masonry Pregrout Passed {Activity date: 02/14/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP
Top out lift for pump house}
02/23/2022 Pool/Spa - Bonding Grip Passed {Activity date: 02/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP. Splash pad}
03/17/2022 COT - LCBU - Preslab Passed {Activity date: 03/17/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - . AP
Area surrounding splash pad approved to pour. All metal poles and columns are bonded to the copper bonding grid in the pre-slab area

} ; {Activity date: 02/23/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA. Splash pad}
03/21/2022 COT - LCBU - Stem Wall/Retaining Wall Passed {Activity date: 03/21/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - APPROVED} ; {Activity date: 02/14/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA} ; {Activity date: 02/08/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Partial approval for retaining wall and 1st lift for pump room ok to place concrete

}
05/26/2022 COT - LCBU - Framing Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - 1090.Approved}
05/26/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - 1090.Approved} ; {Activity date: 03/10/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval for footing south east retaining wall at entrance, ok to place concrete} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
5 footings for the splash-pad canopy approved to pour} ; {Activity date: 02/23/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA splash pad} ; {Activity date: 02/23/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 01/31/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for pump house footer, ok to place concrete}
05/26/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - 1090.Approved} ; {Activity date: 02/01/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval for return lines from pad to pump house

} ; {Activity date: 01/26/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval ok to cover pressure lines on west side of pad no DWV Test} ; {Activity date: 01/21/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CA}
05/26/2022 COT - LCEL - Electrical Final Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 05/23/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel other inspections} ; {Activity date: 05/23/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled}
05/26/2022 COT - LCBU - Building Progress Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - 1090.Approved} ; {Activity date: 03/21/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Canceled} ; {Activity date: 03/21/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 01/26/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval for ground wire and electric from splash pad to pump house ok to cover} ; {Activity date: 11/05/2021; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by ESTEVEN1 - }
05/26/2022 COT - LCPL - Yard Water Line Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - 1090.Approved} ; {Activity date: 01/21/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - PA
All water lines to new splash-pad ok to cover. Tested at 34psi.}
05/26/2022 COT - LCPL - Plumbing Final Passed {Activity date: 05/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 05/23/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - NR
Cancel other inspections}