Outstanding Activity Conditions

Permit Number - T21CM00714
Permit Status: Expired
Permit Description: SFR DRHOX30M19 T19-M0165
Total Outstanding Activity Conditions - 1
Date Name
01/22/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T21CM00714
Permit Description: SFR DRHOX30M19 T19-M0165
Total Completed Inspections - 22
Date Description Inspector Results Comments
02/12/2021 COT - RSPL - Yard Water Line Passed {Activity date: 02/12/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } ; {Activity date: 01/28/2021; Status: Denied; Inspector: RBOOHER; Comment: Entered by VLEON1 - DENIED ADDRESS DOES NOT MATCH PERMIT NUMBER}
02/12/2021 COT - RSPL - Sewer Passed {Activity date: 02/12/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } ; {Activity date: 01/28/2021; Status: Denied; Inspector: RBOOHER; Comment: Entered by VLEON1 - DENIED ADDRES POSTED DOES NOT MATCH PERMIT NUMBER}
02/12/2021 COT - RSPL - Rough Soil Passed {Activity date: 02/12/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } ; {Activity date: 01/28/2021; Status: Denied; Inspector: RBOOHER; Comment: Entered by VLEON1 - DENIED ADDRESS DOES NOT MATCH PERMIT NUMBER}
03/01/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 03/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED}
03/01/2021 COT - RSBU - Preslab Passed {Activity date: 03/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED}
03/01/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 03/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - CODE ECO}
03/01/2021 COT - RSEL - Electrical Underground Passed {Activity date: 03/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED}
03/01/2021 COT - RSEL - Construction Power Passed {Activity date: 03/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED}
03/01/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/01/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - APPROVED}
05/07/2021 COT - RSBU - Roof Nailing Passed {Activity date: 05/07/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/05/2021; Status: Denied; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Denied, corrections incomplete see previous notes.} ; {Activity date: 05/03/2021; Status: Denied; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Denied, Multiple shiners and missed nailing for roof sheathing. Note: Re inspection will be assessed for third Denial if corrections incomplete prior to next inspection
}
05/07/2021 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 05/07/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/05/2021; Status: Denied; Inspector: DMUNIZ; Comment: Entered by VLEON1 - Denied, corrections incomplete see previous notes.} ; {Activity date: 05/03/2021; Status: Denied; Inspector: DMUNIZ; Comment: Entered by VLEON1 - denied,nail shear walls correctly and install missing clips.Install king studs on 1st floor where needed for correct load path and support for Girders. - Note: Re inspection will be assessed for third Denial if corrections incomplete prior to next inspection}
08/13/2021 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 08/13/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved

}
08/13/2021 COT - BULD - SWG Clearance Passed {Activity date: 08/13/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - CODE}
08/13/2021 COT - RSPL - Gas Pressure Test Passed {Activity date: 08/13/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved

}
11/12/2021 COT - RSME - Mechanical Final Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}
11/12/2021 COT - LCBU - Framing Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}
11/12/2021 RSBU - Building Final Passed {Activity date: 11/12/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}
11/12/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}
11/12/2021 COT - RSEL - Outdoor Lighting Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved 2090}
11/12/2021 COT - RSPL - Plumbing Final Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}
11/12/2021 RSME - Mechanical Progress Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}
11/12/2021 COT - RSEL - Electrical Final Passed {Activity date: 11/12/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - approved}

Documents

File Name Document Type  
INSULATION CERTIFICATE.PDF DOCUMENTS VIEW
POST-TENSION SPECIAL INSPECTION REPORT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
MODEL APP.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
WASTEWATER.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF CONSTRPLANS VIEW