Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Residential Building - One or Two Family
Apply Date:
01/22/2021
Applicant:
Description:
SFR SALT165018 T18-M0002

Outstanding Activity Conditions

Permit Number - T21CM00707
Permit Status: Expired
Permit Description: SFR SALT165018 T18-M0002
Total Outstanding Activity Conditions - 3
Date Name
01/22/2021 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
01/22/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
01/22/2021 SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED.

Completed Inspections

Permit Status: Expired
Permit Number: T21CM00707
Permit Description: SFR SALT165018 T18-M0002
Total Completed Inspections - 21
Date Description Inspector Results Comments
02/23/2021 COT - RSPL - Yard Water Line Passed {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED}
02/23/2021 COT - RSPL - Sewer Passed {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED}
02/23/2021 COT - RSPL - Rough Soil Passed {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED}
02/26/2021 COT - RSEL - Grounding/Bonding Passed {Activity date: 02/26/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED}
02/26/2021 COT - RSBU - Preslab Passed {Activity date: 02/26/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED}
02/26/2021 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 02/26/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED}
03/30/2021 COT - RSBU - Roof Nailing Passed {Activity date: 03/30/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - }
03/30/2021 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed {Activity date: 03/30/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - }
04/12/2021 PDSD Building Division - TEP PM Clearance Passed {Activity date: 04/12/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - CODE TMPP}
04/12/2021 COT - RSEL - Construction Power Passed {Activity date: 04/12/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - AP TMPP} ; {Activity date: 04/01/2021; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by VLEON1 - }
06/29/2021 COT - LCBU - Framing Passed {Activity date: 06/29/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - }
06/29/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 06/29/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - }
06/29/2021 RSME - Mechanical Progress Passed {Activity date: 06/29/2021; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VLEON1 - }
03/08/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 1090}
03/08/2022 COT - RSME - Mechanical Final Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/08/2022 RSBU - Building Final Passed {Activity date: 03/08/2022; Status: Partial Approval; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - APPROVED BY INSPECTOR AWAITING CONDITIONS} ; {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/08/2022 COT - RSEL - Outdoor Lighting Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/08/2022 COT - RSEL - Electrical Underground Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 2090}
03/08/2022 COT - RSPL - Plumbing Final Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/08/2022 RSPL - Plumbing Progress Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP 3090}
03/08/2022 COT - RSEL - Electrical Final Passed {Activity date: 03/08/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
WASTEWATER RECEIPT.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
WASTEWATER.PDF DOCUMENTS VIEW
PLOT PLAN.PDF CONSTRPLANS VIEW