Permit: T21CM00696
Permit Details
Apply Date:
01/22/2021
Applicant:
LENNAR ARIZONA CONSTRUCTION INC **APA**
Description:
SFR LENNVC352 T20-M0029
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC **APA**
Completed Inspections
Permit Status: Final
Permit Number: T21CM00696
Permit Description: SFR LENNVC352 T20-M0029
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2021 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved |
| 01/29/2021 | PLUMBING - YARD WTR LINE/TEST | WGALLAGHER | Approved | Approved |
| 01/29/2021 | PLUMBING - SEWER HCS CONNECT | WGALLAGHER | Approved | Approved |
| 02/17/2021 | ELECTRIC - UNDERGROUND | TTREMBULAK | Approved | Not applicable. |
| 02/17/2021 | ELECTRIC - UFER | TTREMBULAK | Approved | Approved |
| 02/17/2021 | BUILDING PRE-SLAB | TTREMBULAK | Approved | Approved |
| 02/17/2021 | EXCAVATION/LAYOUT REBAR & ZON | TTREMBULAK | Approved | Approved |
| 03/02/2021 | ROOF NAILING | RCHANDLER | Approved | APPROVED |
| 03/02/2021 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | APPROVED |
| 04/08/2021 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
| 04/08/2021 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | |
| 04/22/2021 | GAS CLEARANCE | DMUN IZ | Approved | CODE |
| 04/22/2021 | MECHANICAL - INTERMEDIATE | DMUN IZ | Approved | |
| 04/22/2021 | PLUMBING - GAS PRESSURE TEST | DMUN IZ | Approved | |
| 04/22/2021 | PLUMBING - INTERMEDIATE | DMUN IZ | Approved | |
| 04/22/2021 | RESIDENTIAL INTERMEDIATE | DMUN IZ | Approved | |
| 04/22/2021 | FRAMING | DMUN IZ | Approved | |
| 05/04/2021 | SHEET ROCK NAILING | DMUNIZ | Approved | |
| 07/12/2021 | ELECTRIC - FINAL | DMUNIZ | Approved | Approved |
| 07/12/2021 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | Approved |
| 07/12/2021 | PLUMBING - FINAL | DMUNIZ | Approved | Approved |
| 07/12/2021 | MECHANICAL - FINAL | DMUNIZ | Approved | Approved |
| 07/21/2021 | BUILDING - FINAL | KEN | Approved | cert filed |