Permit: T21CM00673
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
6841 E VIA ARROYO LARGO
Address NEW:
6841 E VIA ARROYO LARGO
Apply Date:
01/22/2021
Applicant:
Description:
SFR LENN400219 T19-M0121, 293 LF 6 FT HIGH PATIO WALL
Permit Reviews
Permit Number - T21CM00673
Permit Status: Expired
Permit Description: SFR LENN400219 T19-M0121, 293 LF 6 FT HIGH PATIO WALL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 01/28/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM00673
Permit Status: Expired
Permit Description: SFR LENN400219 T19-M0121, 293 LF 6 FT HIGH PATIO WALL
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/22/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 01/22/2021 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 01/22/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 02/02/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T21CM00673
Permite Description: SFR LENN400219 T19-M0121, 293 LF 6 FT HIGH PATIO WALL
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T21CM00673
Permit Description: SFR LENN400219 T19-M0121, 293 LF 6 FT HIGH PATIO WALL
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2021 | COT - RSPL - Yard Water Line | Passed | {Activity date: 02/11/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} | |
| 02/11/2021 | COT - RSPL - Sewer | Passed | {Activity date: 02/11/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} | |
| 02/11/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 02/11/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - APPROVED} | |
| 02/23/2021 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 02/23/2021 | COT - RSBU - Preslab | Passed | {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 02/23/2021 | COT - RSEL - Electrical Underground | Passed | {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 02/23/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 02/23/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
| 03/22/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 03/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 03/22/2021 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 03/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 05/17/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - CODE TMPP} | |
| 05/17/2021 | COT - RSEL - Construction Power | Passed | {Activity date: 05/17/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 05/25/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 05/25/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 08/04/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/04/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - 1090--AP} ; {Activity date: 05/18/2021; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VLEON1 - PA. Per builder, an AAV will be installed at Eastern lav of Master Bathroom in lieu of approved plan layout. Reschedule eith final inspections to vetify.} ; {Activity date: 05/17/2021; Status: Denied; Inspector: RCHANDLER; Comment: Entered by VLEON1 - DE. 1-Provide nail protection at base plate in Laundry Room. 2-Provide vent connection for lav in Master Bathroom, per plans.} | |
| 08/04/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 08/04/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP} ; {Activity date: 08/03/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled by contractor} | |
| 08/04/2021 | COT - LCBU - Framing | Passed | {Activity date: 08/04/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - 1090--AP} ; {Activity date: 05/18/2021; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 05/17/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 05/17/2021; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 08/04/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 08/04/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP} ; {Activity date: 08/03/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled by contractor} | |
| 08/04/2021 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/04/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - 3090-1090--AP} ; {Activity date: 05/18/2021; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } ; {Activity date: 05/17/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 05/17/2021; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by VLEON1 - } | |
| 08/04/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 08/04/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP} ; {Activity date: 08/03/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled by contractor} | |
| 08/05/2021 | COT - BULD - SWG Clearance | Passed | {Activity date: 08/05/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by RSALDAT1 - CODE} |