Permit: T21CM00395
Permit Details
Apply Date:
01/14/2021
Applicant:
Description:
New warehouse storage building
Permit Reviews
Permit Number - T21CM00395
Permit Status: Issued
Permit Description: New warehouse storage building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/15/2021 | 3RD PARTY REVIEW - COMMERCIAL | 04/06/2021 | COMPLETED |
| 04/06/2021 | RESUBMITTAL | 04/09/2021 | COMPLETED |
| 09/01/2021 | REVISION - - 1ST | 09/20/2021 | COMPLETED |
| 02/10/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/22/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM00395
Permit Status: Issued
Permit Description: New warehouse storage building
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 02/12/2021 | Solid waste enclosure easment must be provided and approved before final inspections. |
| 02/12/2021 | Recorded solid waste enclosure easement must be submitted and approved before final inspections and CofO. |
| 04/06/2021 | SPECIAL INSPECTION IS REQUIRED FOR OUTDOOR LIGHTING |
Conditions
Permit Number - T21CM00395
Permit Status: Issued
Permit Description: New warehouse storage building
| Date | Description | Comments |
|---|---|---|
| 04/06/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 04/06/2021 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 04/06/2021 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 04/06/2021 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 04/06/2021 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 04/06/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 04/06/2021 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 04/06/2021 | SPECIAL INSPECTION IS REQUIRED FOR MASONRY |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM00395
Permite Description: New warehouse storage building
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM00395
Permit Description: New warehouse storage building
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/20/2021 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} ; {Activity date: 10/13/2021; Status: Cancelled; Inspector: DQUINN; Comment: Entered by NGARCIA3 - ca Per Barry} |
|
| 10/20/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/20/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap} ; {Activity date: 10/13/2021; Status: Cancelled; Inspector: DQUINN; Comment: Entered by NGARCIA3 - ca Per Barry} |
|
| 01/06/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 01/06/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 01/27/2022 | COT - LCBU - Preslab | Passed | {Activity date: 01/27/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
| 02/14/2022 | COT - LCPL - Sewer | Passed | {Activity date: 02/14/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Rough from building to hcs ok to backfill.} |
|
| 07/05/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 07/05/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to apply three part roofing system. } |
|
| 09/01/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCPL - Plumbing Roof Drains | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 09/01/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 09/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved} | |
| 10/18/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 12/27/2022 | COT - LCEL - Construction Power | Passed | ||
| 01/27/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 01/27/2023 | COT - LCME - Mechanical Final | Passed | ||
| 01/27/2023 | COT - FCON - Fire - Final | Passed | ||
| 01/27/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
| 01/27/2023 | COT - LCEL - Electrical Underground | Passed | ||
| 01/27/2023 | COT - LCBU - Stem Wall/Retaining Wall | Passed | ||
| 01/27/2023 | COT - LCBU - Masonry Pregrout | Passed | ||
| 02/03/2023 | COT - LCBU - Building Final | Passed | ||
| 02/03/2023 | COT - LCEL - Electrical Final | Passed |