Permit: T21CM00201
Permit Details
Apply Date:
01/06/2021
Applicant:
Ana Liz Chavez
Description:
SFR
Contractors:
- SUNSET WEST CONSTRUCTION LLC
Permit Reviews
Permit Number - T21CM00201
Permit Status: Final
Permit Description: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 02/22/2021 | COMPLETED |
| 02/22/2021 | RESUBMITTAL | 03/11/2021 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T21CM00201
Permit Description: SFR
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2021 | ELECTRIC - UFER | TGAUSP | Approved | |
| 03/19/2021 | BUILDING PRE-SLAB | TGAUSP | Approved | |
| 03/19/2021 | EXCAVATION/LAYOUT REBAR & ZON | TGAUSP | Approved | APPROVED OK TO POUR |
| 03/31/2021 | ROOF NAILING | ESTEVENS | Approved | Approved. |
| 04/02/2021 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Approved. |
| 04/20/2021 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
| 04/20/2021 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
| 04/21/2021 | FRAMING | ESTEVENS | Approved | |
| 04/26/2021 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO |
| 04/26/2021 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | |
| 07/13/2021 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Approved |
| 07/16/2021 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
| 07/16/2021 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 07/16/2021 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 07/16/2021 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
| 08/16/2021 | MECHANICAL - FINAL | TGAUSP | Approved | Approved |
| 08/16/2021 | PLUMBING - FINAL | TGAUSP | Approved | Approved |
| 08/16/2021 | OUTDOOR LIGHTING FINAL | TGAUSP | Approved | 2090 |
| 08/16/2021 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
| 08/16/2021 | BUILDING - FINAL | TGAUSP | Approved | Approved |