Permit: T21CM00071
Permit Details
Apply Date:
01/04/2021
Applicant:
Tucson Expediting & Development
Description:
Ambulatory Surgery Center
Architects:
- Carl Benjamin Nelson
Contractors:
- Kraus Anderson
Permit Reviews
Permit Number - T21CM00071
Permit Status: C of o
Permit Description: Ambulatory Surgery Center
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/05/2021 | 3RD PARTY REVIEW - COMMERCIAL | 03/25/2021 | COMPLETED |
| 03/26/2021 | RESUBMITTAL | 04/06/2021 | COMPLETED |
| 05/19/2022 | REVISION - - 4TH | 06/09/2022 | COMPLETED |
| 06/29/2021 | 3RD PARTY REVIEW - REVISION/OTHER | 08/26/2021 | COMPLETED |
| 09/03/2021 | REVISION - - 2ND | 09/22/2021 | COMPLETED |
| 10/20/2021 | REVISION - - 3RD | 11/09/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM00071
Permit Description: Ambulatory Surgery Center
Total Completed Inspections - 47
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2021 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 07/13/2021 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | AP |
| 08/17/2021 | PLUMBING - ROUGH, SOIL | WGALLAGHER | Approved | Approved under slab |
| 08/23/2021 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | AP |
| 08/31/2021 | BUILDING PRE-SLAB | WGALLAGHER | Approved | Partial approval under roof main building ok to place concrete |
| 08/31/2021 | PLUMBING - PRE SLAB | WGALLAGHER | Approved | Approved |
| 09/10/2021 | FIRE SPKLR - UG, PIPING, HYDRO | wmotto1 | Approved | 200 lb pressure test and pipe approved ok to burry. |
| 09/10/2021 | PLUMBING - YARD WTR LINE/TEST | WGALLAGHER | Approved | Approved |
| 09/30/2021 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | Approved including Oxygen yard and dumpster enclosure |
| 11/03/2021 | PLUMBING - ROOF DRAINS | TLUNDBERG | Approved | AP |
| 11/05/2021 | EXT METAL CLIPS/EXT SHEATHING | TLUNDBERG | Approved | AP South and west walls |
| 11/16/2021 | ROOF NAILING | TLUNDBERG | Approved | AP Owners 3rd party inspector has approved all decking, insulation board, and membrane for the roofing system. |
| 11/19/2021 | ELECTRIC - INTERMEDIATE | TLUNDBERG | Approved | PA. Same as above |
| 11/19/2021 | FRAMING | TLUNDBERG | Approved | PA. All framing approved that was not inspected on 11/5/21 As noted on page A-101 |
| 12/02/2021 | PLUMBING - ABOVE CEILING | TLUNDBERG | Approved | PA Domestic water approved in rooms 109 & 110 as noted on page A 101. |
| 12/13/2021 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | AP |
| 12/15/2021 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | Partial approval for light pole bases 9 each ok to place concrete |
| 12/15/2021 | SHEET ROCK NAILING | WGALLAGHER | Approved | Partial approval for 136,137, 138,140,141,135,142 east face only, 131 partial for corridor only |
| 12/15/2021 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | Not ready |
| 12/15/2021 | STUCCO MESH | WGALLAGHER | Approved | Approved |
| 12/21/2021 | PLUMBING - INTERMEDIATE | TLUNDBERG | Approved | PA Column lines A thru E & column lines 1 thru 7 Domestic hot and cold |
| 12/22/2021 | PLUMBING - MEDICAL GAS/TEST | TLUNDBERG | Approved | PA The following med-gas lines were tested in wall at 150 psi Nitrous Oxide,Carbon Dioxide,Med Air,WAGD,Oxygen,Med Vacuum. |
| 01/12/2022 | FIRE SPKLR - OH PIPING & HYDRO | jfordney | Approved | 205 psi |
| 02/23/2022 | TEP CLEARANCE - AM | WGALLAGHER | Approved | CODE ECO |
| 03/22/2022 | GAS CLEARANCE | WGALLAGHER | Approved | CODE |
| 03/22/2022 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | Approved ok for clearance SWG |
| 03/25/2022 | U VALUE FOR WINDOW | WGALLAGHER | Approved | Approved |
| 04/01/2022 | ELECTRIC - CABLE DROP | WGALLAGHER | Approved | Approved |
| 04/01/2022 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 04/14/2022 | PLUMBING - MD GAS/PRECONST MTG | TLUNDBERG | Approved | AP |
| 04/15/2022 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 04/25/2022 | PLUMBING - FINAL | TLUNDBERG | Approved | AP |
| 04/27/2022 | ELECTRIC - FINAL | TLUNDBERG | Approved | AP |
| 05/03/2022 | SITE - SEWER | TLUNDBERG | Approved | AP |
| 05/12/2022 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | Approved |
| 06/23/2022 | NPPO - FINAL | MHERNANDEZ | Approved | APPROVED |
| 06/23/2022 | RIGHT OF WAY - FINAL | bmong1 | Approved | NO WORK IN ROW |
| 07/15/2022 | FIRE SPKLR - UG PIPING FLUSH | CGates | Approved | Had been approved by JFordney on 1/12/2022 on permit #T22FC00064 |
| 07/15/2022 | FIRE - FINAL | CGates | Approved | |
| 07/15/2022 | FIRE - ALARM FINAL | CGates | Approved | |
| 07/18/2022 | BUILDING ABOVE CEILING | WGALLAGHER | Approved | Approved |
| 07/18/2022 | MECHANICAL - ABOVE CEILING | WGALLAGHER | Approved | Approved |
| 07/19/2022 | LANDSCAPE - FINAL | DROBERTS | Approved | APPROVED |
| 07/22/2022 | ENGINEERING - FINAL | DROBERTS | Approved | IS APPROVED |
| 07/26/2022 | MECHANICAL - FINAL | TLUNDBERG | Approved | AP |
| 07/29/2022 | ELECTRIC - ABOVE CEILING | TLUNDBERG | Approved | AP 2090 |
| 07/29/2022 | BUILDING - FINAL | TLUNDBERG | Approved | AP |