Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address NEW:
1328 E HEDRICK DR 3
Apply Date:
01/04/2021
Applicant:
BOHN, STEPHEN CHARLES
Description:
8 UNIT APARTMENT COMPLEX.
Contractors:
  • LARRY RAY OLSON

Permit Reviews

Permit Number - T21CM00064
Permit Status: C of o
Permit Description: 8 UNIT APARTMENT COMPLEX.
Start Date Submittal Complete Date Status  
01/04/2021 COMMERCIAL - NEW 02/08/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T21CM00064
Permit Status: C of o
Permit Description: 8 UNIT APARTMENT COMPLEX.
Total Outstanding Activity Conditions - 1
Date Name
01/04/2021 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T21CM00064
Permit Description: 8 UNIT APARTMENT COMPLEX.
Total Completed Inspections - 37
Date Description Inspector Results Comments
02/24/2021 PLUMBING - ROUGH, SOIL DQUINN Approved APPROVED
03/05/2021 ELECTRIC - UNDERGROUND DQUINN Approved
03/05/2021 ELECTRIC - UFER DQUINN Approved
03/05/2021 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved
03/11/2021 BUILDING PRE-SLAB DQUINN Approved
03/30/2021 EXT METAL CLIPS/EXT SHEATHING RELEFANTE Approved
06/04/2021 TEP CLEARANCE - AM DQUINN Approved CODE ECO/BLDG #3 ALL LINES TO TRANSFORMERS
06/04/2021 U VALUE FOR WINDOW DQUINN Approved
06/17/2021 MECHANICAL - INTERMEDIATE dquinn Approved
06/17/2021 PLUMBING - INTERMEDIATE dquinn Approved
06/17/2021 ELECTRIC - ABOVE CEILING dquinn Approved
06/17/2021 ELECTRIC - INTERMEDIATE dquinn Approved
06/17/2021 FIREWALL/FIREBARRIER/FIRESTOP dquinn Approved
06/17/2021 FRAMING dquinn Approved
07/15/2021 TEP CLEARANCE - PM DQUINN Approved CODE ECO/ BUILDING 3, ALL UNITS
07/15/2021 ELECTRIC - CONSTRUCTION POWER DQUINN Approved Ap
If there has been no clearance sent yet,
Please clear eco for all units in building #3
11/16/2021 ELECTRIC - FINAL DQUINN Approved Ap C of O nr
11/16/2021 ELECTRIC - OUTDOOR LIGHTING DQUINN Approved Ap
11/16/2021 BUILDING - PROGRESS DQUINN Approved Ap
11/16/2021 BUILDING ABOVE CEILING DQUINN Approved Ap
11/16/2021 ROOF NAILING DQUINN Approved Ap
11/16/2021 ELECTRIC - TEMPORARY SERVICE DQUINN Approved Ap
12/13/2021 STEM WALL/RETAINING WALL DQUINN Approved Ap
12/13/2021 OUTDOOR LIGHTING FINAL DQUINN Approved Ap
12/13/2021 PLUMBING - YARD WTR LINE/TEST DQUINN Approved Ap
12/13/2021 PLUMBING - SEWER HCS CONNECT DQUINN Approved Ap
12/13/2021 MECHANICAL - ABOVE CEILING DQUINN Approved Ap
12/13/2021 FIRE SPKLR - UG, PIPING, HYDRO DQUINN Approved Ap
The 1 above inspection was approved by me - per instructions from
C Basaldua
12/20/2021 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
12/21/2021 FIRE - FINAL DQUINN Approved na
12/21/2021 FIRE SPKLR - FINAL DQUINN Approved na
12/21/2021 FIRE SPKLR - OH PIPING & HYDRO DQUINN Approved na
12/21/2021 FIRE SPKLR - UG PIPING FLUSH DQUINN Approved na. - results are on a separate fire permit
12/21/2021 MECHANICAL - UNDERGROUND DQUINN Approved na
12/21/2021 PLUMBING - FINAL DQUINN Approved Ap
12/27/2021 BUILDING - FINAL DQUINN Approved Ap
12/27/2021 CERTIFICATE OF OCCUPANCY DQUINN Approved Ap
Close permit and ok for C of O

Documents

File Name Document Type  
T21CM00064 AIR BALANCE1.PDF DOCUMENTS VIEW
T21CM00064 WATER REPORT1.PDF DOCUMENTS VIEW
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
GCL - BOND EXEMPTION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COFO.PDF DOCUMENTS VIEW
GCL BOND EXEMPTION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW