Permit Details
Status:
Final
Type:
Barricade and Excavation
Apply Date:
11/05/2020
Applicant:
TUCSON ELECTRIC POWER **B
Description:
TEP WILL BE INSTALLING 1 PAD MOUNT SWITCHGEAR CABINET, 1 RUN OF UNDERGROUNG FEEDER ACROSS BROADWAY (TO BE BORED) AND ONE NEW RISER ON THE SOUTHSIDE OF BROADWAY. TEP WILL ALSO BE REPLACING 1 POLE, INSTALLING 1 NEW STEEL POLE AND CHANGING EQUIPMENT ON 3 MORE POLES. THERE WILL BE ON IMPACT TO SIDEWALKS AND THE NEW STEEL POLE IS 20" IN DIAMETER AT THE GROUND LINE.