Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Barricade and Excavation
Address:
450 N PANTANO RD
Apply Date:
09/21/2020
Applicant:
COX COMMUNICATIONS
Description:
Starting on the East side of N. Pantano Rd, South of E. Centre peak Dr. at TEP pole, Overlash going North for 1100', riser down pole,remove and replace old vault, continue North trench / bore 700' to existing PED, placing a 3x3x3 pothole for new vault,from vault pull through existing conduit 25' going East to out of row . BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AND/OR BEA PAULUS AT 520-206-8826 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. A NOTICE OF TEMPORARY HOLIDAY RESTRICTION applies to this permit and will be in effect from Thanksgiving Day to January 3. Due to the increasing traffic volume on many of the City’s roads, it is necessary to restrict lane closures on certain roads during the holiday season.
Contractors:
  • OPTIMUM AZ INC

Outstanding Inspections

Permit Status: Final
Permit Number: T20RW05142
Permite Description: Starting on the East side of N. Pantano Rd, South of E. Centre peak Dr. at TEP pole, Overlash going North for 1100', riser down pole,remove and replace old vault, continue North trench / bore 700' to existing PED, placing a 3x3x3 pothole for new vault,from vault pull through existing conduit 25' going East to out of row . BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AND/OR BEA PAULUS AT 520-206-8826 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. A NOTICE OF TEMPORARY HOLIDAY RESTRICTION applies to this permit and will be in effect from Thanksgiving Day to January 3. Due to the increasing traffic volume on many of the City’s roads, it is necessary to restrict lane closures on certain roads during the holiday season.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/01/2020 TDOT-EXCAV GENERAL INSPECTION N/A Continued Right lane of north bound traffic closed. Working in shoulder. Boring and potholing in dirt. Barrricades up.

Documents

File Name Document Type  
T20RW05142.PDF ROW-RIGHT OF WAY VIEW