Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
Barricade Only
Address:
110 S CHURCH AV
Address NEW:
110 S CHURCH AV
Apply Date:
07/22/2020
Applicant:
TUCSON ELECTRIC POWER **B
Description:
ROAD CLOSURE DUE TO CRANE SET-UP - ANTICIPATED WORK DATES ARE AUGUST 03-04, 2020 TEP WILL NEED TO CLOSE PORTIONS OF CHURCH FOR THE INSTALLATION OF NEW UNDERGROUND FACILITIES REQUIRED TO FEED HSL'S PROJECT THE FLIN. THIS WILL INCLUDE SETTING 3 PAD MOUNT 3 PHASE TRANSFORMERS AND PULLING IN NEW UNDERGROUND PRIMARY CABLE TO FEED THEM, NO DIGGING.

Completed Inspections

Permit Status: Final
Permit Number: T20RW04224
Permit Description: ROAD CLOSURE DUE TO CRANE SET-UP - ANTICIPATED WORK DATES ARE AUGUST 03-04, 2020 TEP WILL NEED TO CLOSE PORTIONS OF CHURCH FOR THE INSTALLATION OF NEW UNDERGROUND FACILITIES REQUIRED TO FEED HSL'S PROJECT THE FLIN. THIS WILL INCLUDE SETTING 3 PAD MOUNT 3 PHASE TRANSFORMERS AND PULLING IN NEW UNDERGROUND PRIMARY CABLE TO FEED THEM, NO DIGGING.
Total Completed Inspections - 1
Date Description Inspector Results Comments
09/03/2020 TDOT-EXCAV GENERAL INSPECTION Bravin Approved Traffic contol weekend set up for crane removal. Full closure of Stone. No issues. Crane was removed.