Permit Details

Status:
Final
Type:
Barricade and Excavation
Apply Date:
06/22/2020
Applicant:
B & F CONTRACTING
Description:
In order to install approximately 236 lf of 8'' CIPP Lining between MH# 8075-06 and 8649-08 B&F will utilize a typical flagger setup. Excavation footage is for Manhole collar installation. Pedrestrain traffic will not be obstructed as the work is in the street. NOTES: ***CONTRACTOR MUST NOTIFY RESIDENTS 48 HOURS IN ADVANCE*** PERMIT ORIGINALLY FOR: 6/08/20 - 7/07/20
Contractors:
  • BORDER TRAFFIC SAFETY LLC
  • HOFFMAN PROPIPE
  • OLSEN PRECAST STRUCTURES

Completed Inspections

Permit Status: Final
Permit Number: T20RW03517
Permit Description: In order to install approximately 236 lf of 8'' CIPP Lining between MH# 8075-06 and 8649-08 B&F will utilize a typical flagger setup. Excavation footage is for Manhole collar installation. Pedrestrain traffic will not be obstructed as the work is in the street. NOTES: ***CONTRACTOR MUST NOTIFY RESIDENTS 48 HOURS IN ADVANCE*** PERMIT ORIGINALLY FOR: 6/08/20 - 7/07/20
Total Completed Inspections - 1
Date Description Inspector Results Comments
07/28/2020 TDOT-EXCAV GENERAL INSPECTION A.Gomez Approved CIPP lining work completed, new concrete manhole collar also placed.

Documents

File Name Document Type  
T20RW03517.PDF ROW-RIGHT OF WAY VIEW