Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20RW02807
Permit Details
Apply Date:
05/15/2020
Applicant:
TUCSON ELECTRIC POWER **B
Description:
TEP will be working in ROW to install a new single phase transformer on pole #202 on the north side of 22nd and complete the work on the underground secondary junction box on the south side of 22nd. TEP will install UG secondary conductor in customer provided duct. BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 24-HOURS PRIOR TO START OF WORK FOR COORDINATION.
Completed Inspections
Permit Status: Final
Permit Number: T20RW02807
Permit Description: TEP will be working in ROW to install a new single phase transformer on pole #202 on the north side of 22nd and complete the work on the underground secondary junction box on the south side of 22nd. TEP will install UG secondary conductor in customer provided duct.
BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 24-HOURS PRIOR TO START OF WORK FOR COORDINATION.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/17/2020 | TDOT-EXCAV GENERAL INSPECTION | A.Gomez | Approved | Electrical work completed. |