Permit: T20RW02565
Permit Details
Apply Date:
05/06/2020
Applicant:
COX COMMUNICATIONS
Description:
FROM TEP POLE E OF 2967 N ALVERNON WAY, BEGIN 629' OF AERIAL OVERLASH 144 CT FIBER HEADING WEST, RISER DOWN AND BEGIN 246' OF PULL THROUGH EXISTING CONDUIT HEADING WEST , RISER UP AND CONTINUE 465' AERIAL OVERLASH 144 CT FIBER HEADING SOUTH . RISER DOWN, HEAD S AND BEGIN 135'TRENCH/BORE, PLACE 3X3' POTHOLE, HEAD W AND CONTINUE 43' TRENCH/BORE. PLACE 4X4' POT HOLE AND NEW COX VAULT.
Contractors:
- OPTIMUM AZ INC
Completed Inspections
Permit Status: Final
Permit Number: T20RW02565
Permit Description: FROM TEP POLE E OF 2967 N ALVERNON WAY, BEGIN 629' OF AERIAL OVERLASH 144 CT FIBER HEADING WEST, RISER DOWN AND BEGIN 246' OF PULL THROUGH EXISTING CONDUIT HEADING WEST , RISER UP AND CONTINUE 465' AERIAL OVERLASH 144 CT FIBER HEADING SOUTH . RISER DOWN, HEAD S AND BEGIN 135'TRENCH/BORE, PLACE 3X3' POTHOLE, HEAD W AND CONTINUE 43' TRENCH/BORE. PLACE 4X4' POT HOLE AND NEW COX VAULT.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/13/2020 | TDOT-EXCAV GENERAL INSPECTION | A.Gomez | Approved | Overlash work completed, observed no damage to existing asphalt or sidewalk. |