Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20RW02306
Permit Details
Apply Date:
04/22/2020
Applicant:
ZAYO GROUP
Description:
INSTALLATION OF FIBER @ 1,435 LF - TUC GREEN ARROW 1 INSTALLATION OF @ 1,435 LF OF NEW FIBER OPTIC CABLE BY MEANS OF BORING AND EXCAVATING ALONG 6TH AV, 12TH ST AND 4TH AV. THIS PROJECT IS LOCATED IN AN ARCHAEOLOGICAL SENSITIVITY ZONE. STOP WORK AND NOTIFY HPO IF ANY BURIED CULTURAL MATERIALS ARE ENCOUNTERED DURING CONSTRUCTION. OTHER ACTIVITIES IN THE AREA, WILL NEED TO COORDINATE TRAFFIC CONTROL SETUP WITH EXISTING SETUP. SEE ADDITIONAL NOTES.
Contractors:
- QUAIL CONSTRUCTION LLC
- R P COMPANIES INC
Completed Inspections
Permit Status: Final
Permit Number: T20RW02306
Permit Description: INSTALLATION OF FIBER @ 1,435 LF - TUC GREEN ARROW 1
INSTALLATION OF @ 1,435 LF OF NEW FIBER OPTIC CABLE BY MEANS OF BORING AND EXCAVATING ALONG 6TH AV, 12TH ST AND 4TH AV.
THIS PROJECT IS LOCATED IN AN ARCHAEOLOGICAL SENSITIVITY ZONE. STOP WORK AND NOTIFY HPO IF ANY BURIED CULTURAL MATERIALS ARE ENCOUNTERED DURING CONSTRUCTION.
OTHER ACTIVITIES IN THE AREA, WILL NEED TO COORDINATE TRAFFIC CONTROL SETUP WITH EXISTING SETUP.
SEE ADDITIONAL NOTES.
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2020 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | All fiber installed by boring. any potholes were backfilled with a slurry material. No issues with any repairs. Only issues were complaints on parking in front of the post office. Job is complete and all issues were resolved |