Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20RW00717
Permit Details
Apply Date:
02/05/2020
Applicant:
EL PASO NATURAL GAS
Description:
CREW WILL REMOVE ASPHALT & DIRT TO EXPOSE AND INSPECT PIPELINE. IF DEFECTS ARE FOUND, CREW WILL REPLACE OR REPAIR THE PIPELINE, BACKFILL W/DIRT TO 12", THEN USE CONCRETE SLURRY. NEW ASPHALT (3") (OR MATCH EXISTING, WHICHEVER IS GREATER) WILL BE APPLIED WHEN ALL DIGS ARE COMPLETE. 12TH Av is under a pavement moratorium, any new asphalt that is disturbed will require a 2" mill and overlay for 50' in each direction from the outside of the cut for all effected travel lanes..
Contractors:
- EPNG MAINTENANCE CREW SUPERINTENDANT
Completed Inspections
Permit Status: Final
Permit Number: T20RW00717
Permit Description: CREW WILL REMOVE ASPHALT & DIRT TO EXPOSE AND INSPECT PIPELINE. IF DEFECTS ARE FOUND, CREW WILL REPLACE OR REPAIR THE PIPELINE, BACKFILL W/DIRT TO 12", THEN USE CONCRETE SLURRY. NEW ASPHALT (3") (OR MATCH EXISTING, WHICHEVER IS GREATER) WILL BE APPLIED WHEN ALL DIGS ARE COMPLETE.
12TH Av is under a pavement moratorium, any new asphalt that is disturbed will require a 2" mill and overlay for 50' in each direction from the outside of the cut for all effected travel lanes..
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/01/2020 | TDOT-EXCAV GENERAL INSPECTION | Bravin | Approved | Kinder Morgan exposed the existing Gas line for inspection, performed all repairs and slurried the excavation. Any concrete repairs on curb and sidewalk were completed. A and S repaved the three in mill yesterday. All mill areas were set by myself and Fin from Kinder Morgan. All repairs completed. No issues |