Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address NEW:
725 W CALLE LERDO
Apply Date:
12/30/2020
Applicant:
Sonia Gonzalez
Description:
Addition & Alterations SFR

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: T20CM09297
Permite Description: Addition & Alterations SFR
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Not Ready
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/04/2023 COT - RSME - Mechanical Final N/A Re-inspection required 1-Install grills. 2-Uncover combustion air grills.
10/04/2023 COT - RSPL - Plumbing Final N/A Re-inspection required 1-Install kitchen sink. 2-Complete T and P line termination.
04/18/2023 RSBU - Building Final N/A Not Ready
10/04/2023 COT - RSEL - Electrical Final N/A Not Ready 1-Move items away from walls to allow inspection.
09/05/2024 COT - RSEL - Construction Power N/A Not Applicable
10/04/2023 COT - RSPL - Yard Water Line N/A Not Ready Line is covered.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: T20CM09297
Permit Description: Addition & Alterations SFR
Total Completed Inspections - 19
Date Description Inspector Results Comments
01/20/2022 COT - RSPL - Rough Soil Passed {Activity date: 01/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to proceed with building pre slab}
01/27/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 01/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 12/08/2021; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR, Demolition of exterior block walls were verified by plan, okay to proceed with construction}
03/17/2022 COT - RSBU - Preslab Passed {Activity date: 03/17/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved}
05/02/2022 COT - RSBU - Masonry Pregrout Passed {Activity date: 05/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved to top of wall bond beam

} ; {Activity date: 04/22/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, okay to grout to bond beam} ; {Activity date: 04/06/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for 1st lift, okay to grout}
09/14/2022 COT - RSBU - Roof Nailing Passed {Activity date: 09/14/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Approved}
10/13/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 10/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE INCR / CUTOVER}
10/13/2022 COT - RSEL - Electrical Underground Passed {Activity date: 10/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved from service panel to pole, okay to backfill progress areas} ; {Activity date: 10/11/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled}
10/13/2022 COT - RSEL - Service Upgrade Passed {Activity date: 10/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, please send INCR Clearance to TEP for the underground electrical cutover

}
10/20/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
10/20/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
10/20/2022 RSME - Mechanical Progress Passed {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
10/20/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
03/28/2024 COT - RSME - Mechanical Final Passed
03/28/2024 COT - RSPL - Plumbing Final Passed
03/28/2024 RSBU - Building Final Passed
03/28/2024 COT - RSEL - Electrical Final Passed
09/05/2024 COT - RSEL - Outdoor Lighting Passed
09/05/2024 COT - RSPL - Yard Water Line Passed
09/05/2024 COT - RSBU - Stem Wall/Retaining Wall Passed Passed, stem walls for new fencing are completed.

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW