Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Address NEW:
309 N CAMERON VIEW PL
Apply Date:
12/30/2020
Applicant:
ALEX ENOCH
Description:
SFR PORT20 T20-M0042

Permit Reviews

Permit Number - T20CM09277
Permit Status: Final
Permit Description: SFR PORT20 T20-M0042
Start Date Submittal Complete Date Status  
12/30/2020 OTHER 01/28/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM09277
Permit Status: Final
Permit Description: SFR PORT20 T20-M0042
Total Outstanding Activity Conditions - 1
Date Name
12/30/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T20CM09277
Permit Description: SFR PORT20 T20-M0042
Total Completed Inspections - 22
Date Description Inspector Results Comments
02/24/2021 PLUMBING - SEWER HCS CONNECT DQUINN Approved APPROVED
02/24/2021 PLUMBING - ROUGH, SOIL DQUINN Approved APPROVED
02/26/2021 ELECTRIC - UNDERGROUND TGAUSP Approved APPROVED
02/26/2021 ELECTRIC - UFER TGAUSP Approved APPROVED
02/26/2021 BUILDING PRE-SLAB TGAUSP Approved APPROVED OK TO POUR
03/15/2021 FRAMING BSTEVENS Approved APPROVED THIS WAS INSPECTED BY DAN QUINN
03/15/2021 ROOF NAILING BSTEVENS Approved APPROVED THIS WAS INSPECTED BY DAN QUINN
03/15/2021 EXT METAL CLIPS/EXT SHEATHING BSTEVENS Approved APPROVED THIS WAS INSPECTED BY DAN QUINN
03/22/2021 PLUMBING - INTERMEDIATE TGAUSP Approved
03/22/2021 MECHANICAL - INTERMEDIATE TGAUSP Approved
03/22/2021 RESIDENTIAL INTERMEDIATE TGAUSP Approved APPROVED OK TO INSULATE AND ROCK
03/30/2021 TEP CLEARANCE - PM DQUINN Approved CODE ECO
03/30/2021 PLUMBING - YARD WTR LINE/TEST DQUINN Approved
03/30/2021 ELECTRIC - CONSTRUCTION POWER DQUINN Approved
06/30/2021 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved APPROVED BY TONY G
06/30/2021 PLUMBING - PROGRESS DQUINN Approved
06/30/2021 MECHANICAL - FINAL DQUINN Approved
06/30/2021 PLUMBING - FINAL DQUINN Approved
06/30/2021 OUTDOOR LIGHTING FINAL DQUINN Approved
06/30/2021 ELECTRIC - FINAL DQUINN Approved
06/30/2021 BUILDING - FINAL DQUINN Approved
09/29/2021 ASSURANCE BBENEDON Approved Approved

Documents

File Name Document Type  
'PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
BOND 2024 MASS-UPLOAD.JPG DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
BOND .JPG DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW