Permit: T20CM08034
Permit Details
Apply Date:
11/13/2020
Applicant:
LENNAR ARIZONA CONSTRUCTION INC **APA**
Description:
SFR LENNVC352 T20-M0029
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC **APA**
Permit Reviews
Permit Number - T20CM08034
Permit Status: Final
Permit Description: SFR LENNVC352 T20-M0029
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/13/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 11/30/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T20CM08034
Permit Status: Final
Permit Description: SFR LENNVC352 T20-M0029
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/13/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T20CM08034
Permit Description: SFR LENNVC352 T20-M0029
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/27/2020 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | Approved |
11/27/2020 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | Approved |
11/27/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Approved |
12/04/2020 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
12/04/2020 | ELECTRIC - UFER | DMUNIZ | Approved | |
12/04/2020 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
12/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
12/18/2020 | ROOF NAILING | TTREMBULAK | Approved | APPROVED |
12/18/2020 | EXT METAL CLIPS/EXT SHEATHING | TTREMBULAK | Approved | APPROVED |
01/27/2021 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | APPROVED |
01/27/2021 | PLUMBING - GAS PRESSURE TEST | WGALLAGHER | Approved | APPROVED |
01/27/2021 | RESIDENTIAL INTERMEDIATE | WGALLAGHER | Approved | APPROVED |
01/27/2021 | FRAMING | WGALLAGHER | Approved | APPROVED |
01/27/2021 | GAS CLEARANCE | WGALLAGHER | Approved | CODE |
01/29/2021 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO |
01/29/2021 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | APPROVED |
01/29/2021 | ELECTRIC - CONSTRUCTION POWER | WGALLAGHER | Approved | APPROVED |
02/17/2021 | SHEET ROCK NAILING | TTREMBULAK | Approved | APPROVED |
04/14/2021 | MECHANICAL - FINAL | WGALLAGHER | Approved | |
04/14/2021 | PLUMBING - FINAL | WGALLAGHER | Approved | |
04/14/2021 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
04/14/2021 | ELECTRIC - FINAL | WGALLAGHER | Approved | |
04/21/2021 | BUILDING - FINAL | BSTEVENS | Approved |