Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM07859
Permit Details
Apply Date:
11/09/2020
Applicant:
Tucson Expediting & Development/Lisa Bowers
Description:
TI: Retail
Architects:
- Robert Sargenti
Contractors:
- EPSTEIN CONSTRUCTION LLC
Permit Reviews
Permit Number - T20CM07859
Permit Status: C of o
Permit Description: TI: Retail
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/10/2020 | COMMERCIAL - TI | 12/22/2020 | COMPLETED |
11/10/2020 | 3RD PARTY REVIEW - COMMERCIAL TI | 01/12/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T20CM07859
Permit Description: TI: Retail
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/02/2021 | PLUMBING - ROUGH, SOIL | RBOOHER | Approved | APPROVED OK TO COVER |
02/04/2021 | PLUMBING - PRE SLAB | RBOOHER | Approved | APPROVED, OK TO POUR SLAB |
02/04/2021 | PLUMBING - PRE SLAB | RBOOHER | Approved | DENIED - ON SITE CONTACT DOES NOT WANT TO SHOW INSPECTOR PRE SLAB PLANS |
02/25/2021 | FRAMING | TGAUSP | Approved | APPROVED REMAINING FRAME WALLS ARE COMPLETE AND APPROVED |
02/25/2021 | PLUMBING - INTERMEDIATE | TGAUSP | Approved | APPROVED |
02/25/2021 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | APPROVED |
02/26/2021 | MECHANICAL - INTERMEDIATE | TGAUSP | Approved | APPROVED |
02/26/2021 | SHEET ROCK NAILING | TGAUSP | Approved | APPROVED |
03/18/2021 | MECHANICAL - ABOVE CEILING | TGAUSP | Approved | |
03/18/2021 | PLUMBING - ABOVE CEILING | TGAUSP | Approved | |
03/18/2021 | ELECTRIC - ABOVE CEILING | TGAUSP | Approved | |
03/18/2021 | BUILDING ABOVE CEILING | TGAUSP | Approved | APPROVED, NO CEILING |
03/23/2021 | FIRE - FINAL | Mross | Approved | Mount second fire extinguisher to post in center of suite |
03/23/2021 | FIRE - ALARM FINAL | Mross | Approved | |
03/23/2021 | FIRE SPKLR - FINAL | Mross | Approved | |
03/24/2021 | BUILDING - FINAL | RSHERRY | Approved | |
03/24/2021 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
03/24/2021 | BUILDING - FINAL | TGAUSP | Approved | Approved. PENDING AIR BAL RPT AP. |
03/24/2021 | ELECTRIC - FINAL | TGAUSP | Approved | Approved |
03/24/2021 | PLUMBING - FINAL | TGAUSP | Approved | Approved, pending water disinfection report approval |
03/24/2021 | MECHANICAL - FINAL | TGAUSP | Approved | Approved, pending air balance report approval |
03/24/2021 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |