Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T20CM07724
Permit Details
Apply Date:
11/05/2020
Applicant:
Description:
SFR LENN400219 T19-M0121
Outstanding Activity Conditions
Permit Number - T20CM07724
Permit Status: Expired
Permit Description: SFR LENN400219 T19-M0121
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
11/05/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
11/05/2020 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
11/05/2020 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T20CM07724
Permite Description: SFR LENN400219 T19-M0121
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T20CM07724
Permit Description: SFR LENN400219 T19-M0121
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/04/2020 | COT - RSPL - Yard Water Line | Passed | {Activity date: 12/04/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
12/04/2020 | COT - RSPL - Sewer | Passed | {Activity date: 12/04/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
12/04/2020 | COT - RSPL - Rough Soil | Passed | {Activity date: 12/04/2020; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by PAHUMAD1 - } | |
12/15/2020 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 12/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
12/15/2020 | COT - RSBU - Preslab | Passed | {Activity date: 12/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
12/15/2020 | COT - RSEL - Electrical Underground | Passed | {Activity date: 12/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
12/15/2020 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 12/15/2020; Status: Approved; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Approved} | |
01/12/2021 | COT - RSBU - Roof Nailing | Passed | {Activity date: 01/12/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/07/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled Please leave accurate contact information when scheduling your inspection} |
|
01/12/2021 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 01/12/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} ; {Activity date: 01/07/2021; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by RSALDAT1 - Inspection canceled Please leave accurate contact information when scheduling your inspection} |
|
02/22/2021 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - CODE ECO} | |
02/22/2021 | COT - RSEL - Construction Power | Passed | {Activity date: 02/22/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - APPROVED} | |
02/24/2021 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 02/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
02/24/2021 | COT - LCBU - Framing | Passed | {Activity date: 02/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
02/24/2021 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 02/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
02/24/2021 | COT - BULD - SWG Clearance | Passed | {Activity date: 02/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - CODE} | |
02/24/2021 | RSME - Mechanical Progress | Passed | {Activity date: 02/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
02/24/2021 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 02/24/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VLEON1 - APPROVED} | |
03/15/2021 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 03/15/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } ; {Activity date: 02/24/2021; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VLEON1 - NOT READY} | |
05/21/2021 | COT - RSME - Mechanical Final | Passed | {Activity date: 05/21/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
05/21/2021 | COT - RSPL - Plumbing Final | Passed | {Activity date: 05/21/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } | |
05/21/2021 | COT - RSEL - Electrical Final | Passed | {Activity date: 05/21/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VLEON1 - } |