Permit: T20CM07528
Permit Details
Apply Date:
10/30/2020
Applicant:
Lisa Bowers
Description:
Electrical & Site Electrical for future Modular
Completed Inspections
Permit Status: Complete
Permit Number: T20CM07528
Permit Description: Electrical & Site Electrical for future Modular
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2021 | COT - LCEL - Construction Power | Passed | {Activity date: 04/23/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 04/23/2021 | COT - LCEL - Temporary Service | Passed | {Activity date: 04/23/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - } | |
| 06/02/2022 | PDSD Building Division - TEP PMÂ Clearance | Passed | {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE ECO} ; {Activity date: 04/23/2021; Status: Approved; Inspector: RELEFANTE; Comment: Entered by VLEON1 - CODE ECO} | |
| 06/02/2022 | COT - LCEL - Service Upgrade | Passed | {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for the 600A switch gear, please send ECO clearance to TEP} | |
| 06/02/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved with ground rods} | |
| 02/25/2025 | COT - LCEL - Electrical Final | Passed | ||
| 02/25/2025 | COT - LCEL - Electrical Underground | Passed | ||
| 02/25/2025 | COT - LCEL - Electrical Intermediate | Passed |