Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Expired
Type:
Commercial Building
Apply Date:
10/29/2020
Applicant:
Description:
PARK SPLASH PAD

Permit Reviews

Permit Number - T20CM07509
Permit Status: Expired
Permit Description: PARK SPLASH PAD
Start Date Submittal Complete Date Status  
10/30/2020 COMMERCIAL - TI 12/07/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T20CM07509
Permit Status: Expired
Permit Description: PARK SPLASH PAD
Total Outstanding Activity Conditions - 1
Date Name
10/29/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Expired
Permit Number: T20CM07509
Permite Description: PARK SPLASH PAD
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
05/13/2021 COT - LCPL - Yard Water Line N/A Canceled {Activity date: 05/13/2021; Status: Not Applicable; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - }
11/04/2022 COT - ENGR - Site - Assurance Release N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T20CM07509
Permit Description: PARK SPLASH PAD
Total Completed Inspections - 14
Date Description Inspector Results Comments
05/13/2021 COT - LCEL - Electrical Underground Passed {Activity date: 05/13/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - }
05/13/2021 Pool/Spa - Bonding Grip Passed {Activity date: 05/13/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - }
05/13/2021 Pool/Spa - Plumbing Passed {Activity date: 05/13/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - }
06/15/2021 COT - LCBU - Preslab Passed {Activity date: 06/15/2021; Status: Approved; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - }
03/24/2022 COT - LCBU - Building Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP}
03/24/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP} ; {Activity date: 06/15/2021; Status: Cancelled; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - CANCELLED WILL RESCHEDULE WHEN READY}
03/24/2022 COT - LCBU - Framing Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP}
03/24/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP} ; {Activity date: 06/15/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - Partial. Splash pad area ok for concrete.} ; {Activity date: 05/26/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - Partial. Seven shade post footings, ok for concrete.
} ; {Activity date: 05/13/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - Partial. Surge tank area ok for concrete.}
03/24/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP}
03/24/2022 COT - LCEL - Electrical Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP}
03/24/2022 ENGR Engineering Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - APPROVED}
03/24/2022 COT - LCBU - Building Progress Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP} ; {Activity date: 06/15/2021; Status: Partial Approval; Inspector: TT; Comment: Entered by VLEON1 - Partial. Splash pad area UFER/BONDING and pre-slab ok for concrete.} ; {Activity date: 05/26/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - Partial. Seven shade post footings, ok for concrete.
}
03/24/2022 COT - LCPL - Plumbing Final Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP}
03/24/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 03/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - 1090.AP} ; {Activity date: 06/15/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - PARTIAL SPLASH PAD AREA OK} ; {Activity date: 05/13/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - Partial. Surge tank area ok for concrete.}

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PAYMENT MEMO.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
STRUC CALCS.PDF DOCUMENTS VIEW